Information Notice No. 91-74: Changes In Pressurizer Safety Valve Setpoints Before Installation
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
November 25, 1991
NRC INFORMATION NOTICE 91-74: CHANGES IN PRESSURIZER SAFETY VALVE SETPOINTS
BEFORE INSTALLATION
Addressees
All holders of operating licenses or construction permits for nuclear power
reactors.
Purpose
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information
notice to alert addressees to excessive changes observed in the setpoints of
pressurizer safety valves (PSVs) after setting and acceptance testing but
before installation. It is expected that recipients will review the
information for applicability to their facilities and consider actions, as
appropriate, to avoid similar problems. However, suggestions contained in
this information notice are not NRC requirements; therefore, no specific
action or written response is required.
Description of Circumstances
The Duke Power Company is investigating excessive changes in Dresser PSV
setpoints that it has frequently identified during post-operational tests.
The investigation has revealed that the setpoint changes may have been
present before installation. Duke Power began the investigation when
testing of as-found PSVs removed from the Catawba and Oconee Nuclear
Stations in refueling outages early in 1991 revealed setpoints significantly
outside the technical specification (TS) tolerance of �1 percent. Each of
five valves tested failed to meet the TS limits, and the average deviation
was over 5 percent (four failed high and one low). While performing
subsequent investigative tests on two valves that had been acceptably set
and tested to the TS criteria, but not installed, Duke found unacceptable
setpoints. One valve setpoint was high by 2.2 percent and the other was
high by 5.6 percent, as compared to the �1 percent TS limit.
In its investigation, Duke initially examined its use of a pre-installation
"jack-and-lap" procedure following setpoint testing as a possible
contributor to the setpoint changes. This procedure involves partial
disassembly of a PSV, maintaining its spring in compression, and polishing
the seat surfaces to remove minor irregularities that may cause seat
leakage. Licensee personnel questioned the adequacy of the controls
previously applied to the jack-and-lap process. Procedural controls were
added and an acceptably set and tested PSV was processed using the revised
jack-and-lap procedure. Calculations indicated that any setpoint change
caused by the new jack-and-lap procedure should
9111180310
.
IN 91-74
November 25, 1991
Page 2 of 5
not exceed 0.5 percent. However, retesting following performance of the new
procedure revealed a setpoint that was 2.2 percent high, which is greater
than a 1 percent change from the previous setting. This is the 2.2 percent
high setpoint previously referred to in the above paragraph. The setpoint
increase beyond the 1 percent TS limit found in this test suggests that the
jack-and-lap procedure has not been wholly responsible for the unreliable
setpoints at the Duke plants. However, the fact that the setpoint deviated
less than was recently experienced indicates that the previous jack-and-lap
procedure may have contributed significantly to the problem.
The valve referred to in the second paragraph above which tested 5.6 percent
high in the pre-installation test had successfully completed the sequence
normally used to prepare the valve as a replacement to be installed during
the next refueling outage. It was obtained from storage at the Catawba
Nuclear Station. Therefore, the licensee had not controlled the
jack-and-lap procedure as closely for this valve as for the one which tested
2.2 percent high.
Duke has identified a number of possible causes of the excessive changes in
PSV setpoints and considers the following two the most probable:
Valve leakage during setpoint testing that is eliminated by the
subsequently performed jack-and-lap procedure:
If a valve is leaking during setpoint testing, its huddle chamber may
become partially pressurized, increasing the valve seat area and
reducing the pressure required to cause lift. The pressure required to
produce lift will be increased above the original setting if personnel
adjust and test the setpoint with this leak and later repair the leak
(through the jack-and-lap process) without verifying the setpoint
again, as was the licensee's practice.
Inadequate control of the jack-and-lap process
The jack-and-lap process involves disassembling the valve partially and
polishing the seating surfaces. This may introduce errors that can be
limited with close controls but that may be inadequately quantified if
the setpoint is not reverified afterward.
Duke considered other possible causes of setpoint change including the
following:
� failure to recognize adverse trends in the three setpoint pops
used in the verification test,
� performance of ring adjustments without reverifying the setpoint,
� temperature effects (as described in NRC Information Notice 89-90,
"Pressurizer Safety Valve Lift Setpoint Shift," and Supplements 1
and 2),
.
IN 91-74
November 25, 1991
Page 3 of 5
� spring performance variables (e.g., corrosion or inadequate
lubrication of spring/spring washer sliding surfaces),
� seat adhesion,
� handling or transportation shock, and
� various test process parameters (e.g., steam quality,
pressurization rate, valve installation variables, equipment
calibration errors, and personnel errors).
Duke reported that, based on its investigation, the refurbishment and test
sequence it plans to specify for its PSVs each refueling outage is as
follows:
� Mount the valve on a test stand and strap on electric heaters and
thermocouples. Two thermocouples to be placed 120� apart at each
of the following locations: valve inlet flange, lower bonnet, and
upper bonnet.
� Supply the valve with saturated steam at 90 percent of the set
pressure for heat-up.
� Allow the steam to heat the valve's internal components while the
heaters and thermocouples are used to maintain the proper valve
temperature.
� Leak test the valve with steam by placing a mirrored surface probe
at the valve discharge and observing its surface for condensation.
Use the following acceptance criterion: "No leakage shall be
allowed."
� If leaking is found, repair the valve by the jack-and-lap process.
� Determine the initial actuation setpoint by raising the steam
pressure at a ramp of 100 to 200 pounds per square inch per second
until the valve stem lifts.
� If the setpoint is not within the specified �1 percent limits,
notify the licensee and adjust the valve setpoint and retest the
valve until it is within the specified limits.
� Require three consecutive successful tests within the specified
setpoint limits for acceptance.
� Leak test the valve with steam at 93 percent of the nameplate
rating by passing a mirrored surface probe around the disc-seat
interface and then visually inspecting the mirror for
condensation. Use the following acceptance criterion: "No
leakage shall be allowed."
� If leaking is found, repair the valve by the jack-and-lap process.
Following repair, install the valve on the steam header and verify
the setpoint.
.
IN 91-74
November 25, 1991
Page 4 of 5
� If leakage is not found following the setpoint verification,
package the valve and transport it to the station for storage
until the next refueling outage.
Subsequent to the investigative tests mentioned above, Duke retested a PSV
for Catawba that had previously been refurbished and set in accordance with
the above sequence and then placed in storage. The setpoint was determined
during five actuations, and each lift was within 1 percent of the original
setpoint. This indicated that the more strictly controlled refurbishment
and testing may help reduce the magnitude of setpoint changes.
Unfortunately, the valve failed the test because of minor leakage.
Discussion
The industry has continued to find that the setpoints of PSVs and main steam
safety and safety relief valves can be unreliable. Recently, the NRC staff
reviewed data from the Nuclear Plant Reliability Data System and found that,
historically, as-found PSVs in U.S. plants have failed over 40 percent of
the setpoint tests performed. The NRC staff believes that the number may
actually be higher because of unreported failures. In performing the
investigation described herein, the Duke Power Company identified possible
causes of setpoint change that may have not been previously given adequate
recognition. This investigation indicates the need to ensure that setpoint
testing is performed after all operations that may cause changes. In this
example, jack-and-lap procedures used to correct leakage before installation
may have caused the setpoints to change. Many licensees prefer not to test
the setpoint after performing procedures to correct leakage (such as the
jack-and-lap) because the setpoint test itself appears to often lead to
subsequent leakage, resulting in a repeating cycle that may be difficult to
end. Leakage itself cannot be tolerated because even small pre-installation
leaks may lead to steam cutting and increasing leakage during operation,
which could cause the setpoint to change during operation. The licensees
may need to maintain closer controls on certain maintenance, setting,
testing, and other operations performed before the valve is installed.
The Duke Power Company investigated setpoint changes on PSVs manufactured by
Dresser Industries, which is understood to have supplied similar valves to
approximately a third of the nuclear utilities in the United States.
However, similar problems may exist with PSVs supplied by other
manufacturers due to similarities in design, setpoint testing, maintenance
practices, leakage correction practices, and other factors.
Related Generic Communications
Previous information notices issued on related topics include IN 86-56,
"Reliability of Main Steam Safety Valves"; IN 86-92, "Pressurizer Safety
Valve Reliability"; IN 88-68, "Setpoint Testing of Pressurizer Safety Valves
with Filled Loop Seals Using Hydraulic Assist Devices"; and IN 89-90 and
Supplements 1 and 2, "Pressurizer Safety Valve Lift Setpoint Shift."
.
IN 91-74
November 25, 1991
Page 5 of 5
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
one of the technical contacts listed below or the appropriate Office of
Nuclear Reactor Regulation (NRR) project manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical contacts: Edward H. Girard, RII Charles G. Hammer, NRR
(404) 331-4186 (301) 492-0791
Francis Jape, RII Mary S. Wegner, AEOD
(404) 331-4182 (301) 492-7818
Attachment: List of Recently Issued NRC Information Notices
.
Page Last Reviewed/Updated Wednesday, March 24, 2021