Information Notice No. 91-13: Inadequate Testing Of Emergency Diesel Generators (EDGs)
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
March 4, 1991
Information Notice No. 91-13: INADEQUATE TESTING OF EMERGENCY
DIESEL GENERATORS (EDGs)
Addressees:
All holders of operating licenses or construction permits for nuclear power
reactors.
Purpose:
This information notice is intended to alert addressees to inadequacies in
the testing of emergency diesel generators at nuclear power plants.
Specifically, some EDG testing has not adequately verified the capability of
the EDG to carry its maximum expected loads and other tests have failed to
properly verify the operation of the load shedding logic for the EDG. These
testing deficiencies indicate that other licensees may have similar
deficiencies that have not yet been detected. It is expected that
recipients will review the information for applicability to their facilities
and consider actions, as appropriate, to avoid similar problems. However,
suggestions contained in this information notice do not constitute NRC
requirements; therefore no specific action or written response is required.
Description of Circumstances:
Yankee Atomic Electric Company, the licensee for the Yankee Nuclear Power
Station (Yankee Rowe), recently identified that the EDGs at the Yankee Rowe
plant were undersized for their maximum accident electrical load demand.
The EDGs failed to reach their technical specification (TS) required loading
of 400 kilowatts (kW) while connected in parallel to the electrical grid.
The licensee then retested the EDGs using a resistor bank in place of the
grid. Using this test configuration, Yankee Atomic determined that the
frequency of the generator dropped to 58 hertz with a maximum electrical
output of 385 kW. The licensee attributed the reduction in power output, in
part, to high ambient air temperatures that reduced engine power and
cooling. The licensee had not considered the effect of ambient air
temperature during previous testing. The existing air temperature was
within design basis limits. Although high ambient air temperature was the
immediate cause of the failure to attain 400 kW, the root cause was the fact
that the engines were undersized. The manufacturer's rating of 400 kW also
failed to consider the effects of ambient air temperature. The licensee
calculated that the dependable capacity of these EDGs was between 359 kW and
399kW. Yankee Atomic eventually replaced all 3 EDGs with models capable of
producing 600 kW (450 kW continuous) because the
9102260165
.
IN 91-13
March 4, 1991
Page 2 of 3
estimated electrical load on the EDGs is very close to 400 kW and
modifications to the original EDGs failed to raise their output
capabilities. The Omaha Public Power District, the licensee for Fort
Calhoun Station, Unit 1, reported a similar problem with their EDGs. At
Fort Calhoun, the EDGs could temporarily achieve their design rating at high
ambient temperatures, but they could not maintain this power level for an
extended period of time.
At the Vermont Yankee Generating Station, during a safety system functional
inspection, the U.S. Nuclear Regulatory Commission (NRC) staff determined
that the surveillance testing of the station EDGs was inadequate. The staff
found that there was insufficient electrical loading during testing as well
as insufficient compensation for the expected electrical power factor (pf).
Specifically, the plant surveillance test for the EDGs required that the
EDGs maintain a load of 2500 to 2750 kW, which is equivalent to 2500 to 2750
kilovolt-amperes (kVA) at pf=1.0. The licensee considered this limit suffi-
cient to meet the maximum load of 2471 kW specified in the final safety
analysis report (FSAR). However, during subsequent analysis, the licensee
determined that the worst-case EDG loading could actually reach 2751 kW. In
addition, the EDG would realistically experience an electrical power factor
of 0.85 lagging, causing the actual generator output current to be
significantly higher (i.e., assuming generator output voltage is maintained
roughly constant, generator output current and kVA at pf=0.85 are
approximately 1.18 times the generator output current and kVA at pf= 1.0.)
Therefore, the existing surveillance did not adequately demonstrate the
capability of the EDG to carry its accident kW and current loading. As a
result, the licensee is modifying its EDG testing requirements to ensure
that both the engine and the generator will be appropriately tested to
demonstrate their capability to produce the accident electrical load.
At Millstone Nuclear Power Station, Unit 3, the Northeast Nuclear Energy
Company (the licensee) determined that its testing of the EDG load shedding
circuitry was inadequate. In particular, the surveillance tests did not
verify the load shedding of five nonsafety-related loads and two
safety-related loads. This condition was a violation of TS requirements and
had existed from initial plant operation in April 1986 until January 1990.
Subsequent testing verified that the load shedding circuits operated
properly.
Discussion:
The events at Yankee Rowe, Fort Calhoun, and Vermont Yankee illustrate the
failure of EDG testing to demonstrate properly the capability of the EDGs to
assume the design-basis electrical loading during an accident. The intent
of the required surveillance testing is to assure that the EDG can
dependably carry its accident loads. It is important that the worst-case
conditions (frequency, voltage, electrical power factor, and environment) be
considered when the EDG is tested. In particular, the effects of the
electrical power factor and the environment may have been overlooked. It is
important that procedures give personnel performing the test sufficient
information to allow them to load the EDG to simulate worst-case conditions.
Since the simulation of environmental conditions is generally impractical,
it may be necessary to use analysis to correct for environmental conditions
or to show that the effect
.
IN 91-13
March 4, 1991
Page 3 of 3
of such conditions is negligible for the EDG. Information from the vendor
may help in determining what changes, if any, may be necessary. It is also
important for procedures to give adequate guidance to ensure that the EDG is
not inadvertently overloaded during the test.
The last event illustrates the failure of EDG testing to verify adequately
the proper operation of all of the logic necessary to support the EDG in an
accident. Millstone Unit 3 was given as an example, but other similar cases
have been reported.
Generic Letter 88-15, "Electric Power Systems - Inadequate Control Over
Design Processes," discussed problems similar to those in this information
notice.
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
one of the technical contacts listed below or the appropriate NRR project
manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical Contacts: C. H. Woodard, Region I
(215) 337-5261
A. J. Kugler, NRR
(301) 492-0834
Attachment: List of Recently Issued NRC Information Notices
.
Page Last Reviewed/Updated Thursday, March 25, 2021