503rd ACRS Meeting, June 12-13, 2003

May 19, 2003

SCHEDULE AND OUTLINE FOR DISCUSSION
503rd ACRS MEETING
JUNE 12-13, 2003

THURSDAY, JUNE 12, 2003, CONFERENCE ROOM 2B3, TWO WHITE FLINT NORTH, ROCKVILLE, MARYLAND
1) 8:30 - 8:35 A.M. Opening Remarks by the ACRS Chairman (Open)
    1.1) Opening Statement (MVB/JTL/SD)
    1.2) Items of current interest (MVB/SD)
2) 8:35 - 6:00 P.M. WORKSHOP ON SAFETY CULTURE (Open) (GEA/MWW/MME)
    2.1) 8:35 - 8:45 A.M. - Introductory Statement - Remarks by the Subcommittee Chairman regarding the scope, outline, and anticipated outcome of the Workshop.
    2.2) 8:45 - 12:45 P.M. [10:00-10:15 A.M. BREAK] - Panel A - Collective Understanding of Safety Culture (Open)
Presentations by and discussions with representatives of the NRC staff, nuclear industry, private consultants, and public regarding collective understanding of safety culture.
   12:45 - 1:45 P.M. ***LUNCH***
    2.3) 1:45 - 5:00 P.M. [3:20-3:35 P.M. BREAK] - Panel B - Attributes of Safety Culture (Open)
Presentations by and discussions with representatives of the NRC staff, nuclear industry, private consultants, and public regarding attributes of safety culture.
    2.4) 5:00 - 6:00 P.M. - Conclusions and Outcome of the Workshop (Open) - Discussion of conclusions resulting from the Workshop
FRIDAY, JUNE 13, 2003, CONFERENCE ROOM 2B3, TWO WHITE FLINT NORTH, ROCKVILLE, MARYLAND
3) 8:30 - 8:35 A.M. Opening Remarks by the ACRS Chairman (Open) (MVB/JTL/SD)
4) 8:35- 10:00 A.M. Update to Generic License Renewal Guidance Documents (Open) (GML/MVB/SD)
    4.1) Remarks by the Subcommittee Chairman
    4.2)

Briefing by and discussions with representatives of the NRC staff regarding potential improvements to license renewal guidance documents (Generic Aging Lessons Learned Report; Regulatory Guide 1.188, Standard Format and Content for Applications to Renew Nuclear Power Plant Operating Licenses; Standard Review Plan for Review of License Renewal Applications; and NEI 95-10, Industry Guideline for Implementing the Requirements of 10 CFR Part 54).

Representatives of the nuclear industry may provide their views, as appropriate.

5) 10:00 - 10:30 A.M. Subcommittee Report on the Fort Calhoun License Renewal Application (Open) (MVB/GML/RC)
    Report by the Subcommittee Chairman regarding the Subcommittee's review of the license renewal application for the Fort Calhoun Station Unit 1 and the associated NRC staff's Safety Evaluation Report.
   10:30 - 10:45 A.M. ***BREAK***
6) 10:45 - 11:45 A.M. Proposed Strategy for Preparing the 2004 ACRS Report on the NRC Safety Research Program (Open) (DAP/RPS/HSN)
Report by the Chairman of the Safety Research Program Subcommittee regarding a proposed strategy for preparing the 2004 ACRS report on the NRC Safety Research Program.
   11:45 - 12:45 P.M. ***LUNCH***
7) 12:45 - 1:45 P.M.
Future ACRS Activities/Report of the Planning and Procedures Subcommittee (Open) (MVB/JTL/SD)
    7.1) Discussion of the recommendations of the Planning and Procedures Subcommittee regarding items proposed for consideration by the full Committee during future ACRS meetings.
    7.2) Report of the Planning and Procedures Subcommittee on matters related to the conduct of ACRS business, including anticipated workload and member assignments.
8) 1:45 - 2:00 P.M. Reconciliation of ACRS Comments and Recommendations (Open) (MVB, et al./SD, et al.)
Discussion of the responses from the NRC Executive Director for Operations to comments and recommendations included in recent ACRS reports and letters.
   2:00 - 2:15 P.M. ***BREAK***
9) 2:15 - 6:30 P.M. Preparation of ACRS Reports (Open)
Discussion of the proposed ACRS reports on:
    9.1) Safety Culture Report (GEA/MWW)
    9.2) Update to Generic License Renewal Guidance Documents
(GML/MVB/SD)
    9.3) Safeguards and Security (Closed) (GEA/RPS). This session will be held in Room T-8E8
10) 6:30 - 7:00 P.M. Miscellaneous (Open) (MVB/JTL)
    Discussion of matters related to the conduct of Committee activities and matters and specific issues that were not completed during previous meetings, as time and availability of information permit.

Note:

  • Presentation time should not exceed 50 percent of the total time allocated for a specific item. The remaining 50 percent of the time is reserved for discussion.
  • Thirty-Five (35) copies of the presentation materials should be provided to the ACRS.

Page Last Reviewed/Updated Wednesday, July 20, 2016