Project Overview
The SMR-160 is a pressurized water reactor (PWR) with passive safety systems designed by SMR, LLC, a Holtec International Company. The reactor, steam generator, and spent fuel pool are located in containment with the reactor core well below grade. The SMR-160 has a rated electrical output of 160 MWe.
Pre-Application Documents for the SMR-160 Design
The U.S. Nuclear Regulatory Commission (NRC) considers public involvement in, and information about, our activities to be a cornerstone of strong, fair regulation of the nuclear industry. As such, the NRC believes that nuclear regulation should be transacted as openly and candidly as possible to maintain and enhance the public's confidence. Ensuring appropriate openness explicitly recognizes that the public must be informed about, and have a reasonable opportunity to participate meaningfully in, the NRC's regulatory processes. Toward that end, this page provides access to documents and correspondences related to the pre-application activities with SMR, LLC, a Holtec International Company, regarding its initial design, SMR-160.
On this page:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Topical Reports for the SMR-160
The following table provides access to topical reports that SMR (Holtec) has submitted for NRC staff review and approval:
During the review of the topical reports (TRs), the NRC staff may issue requests for additional information (RAIs) that are needed to determine the acceptability of methods and approaches described in each TR. The applicant's responses to RAIs may result in revisions to a TR and the issuance of TR supplement that incorporates all changes. Only the latest revision of the TR is listed above.
Additional information can be obtained from ADAMS using a search by docket number 99902049.
White Papers for the SMR-160 Design
The following table provides access to White Papers that SMR (Holtec) has submitted for NRC staff review and feedback:
Submittal Date |
Title |
White Paper ADAMS Accession No. |
Staff Feedback or Assessment ADAMS Accession No. |
08/25/23 |
SMR, LLC/Mitsubishi Electric Corp., JEXK-0143-1049-P(R0), “Two Division Safety System Compliance with Applicable Rules and Regulations” |
Proprietary |
See 09/13/23 Meeting Summary |
08/11/23 |
SMR, LLC/Mitsubishi Electric Corp., JEXK-0143-1050-P(R0), “Functional Independence Evaluation Based on ISG-04” |
Proprietary |
See 08/23/23 Meeting Summary |
07/13/23 |
SMR, LLC JEXK-0143-1048-P, "Diversity Evaluation Based on NUREG/CR-6303." |
Proprietary |
See 07/26/23 Meeting Summary |
06/14/23 |
SMR, LLC Report HI-2210328, "HFE Functional Requirements Analysis and Function Allocation for Chemical and Volume Control System" |
Proprietary |
See 06/20/23 Meeting Summary |
05/23/23 |
SMR, LLC Report Hl-2230397 Rev. 0, SMR-160 LOCA Exemption Request Language and Acceptance Criteria White Paper for May 25, 2023 |
Proprietary |
See 05/25/23 Meeting Summary |
05/11/23 |
SMR, LLC Report HI-2210473, Revision 0, "SMR-160 PSA Risk Significance Determination Methodology" |
Proprietary |
See 05/17/23 Meeting Summary |
03/29/23 |
SMR, LLC Report Hl-2230279 Rev. 0, LOCA Exemption Update White Paper (P) |
ML23088A028 |
See 04/05/23 Meeting Summary |
01/23/23 |
SMR, LLC, SMR-160 Hazard Analysis for l&C System Methodology Report No. Hl‑2230060, Rev. 0 |
ML23023A006, part of ML23023A002 |
See 02/08/23 Meeting Summary |
12/19/22 |
SMR, LLC, Preapplication Meeting Materials for January 25, 2023 |
ML22353A297 |
See 01/25/23 Meeting Summary |
12/19/22 |
SMR-160 Reactor Coolant Makeup White Paper |
ML22353A294 |
See 01/11/23 Meeting Summary |
11/01/22 |
Enclosure 2: SMR-160 PDHR and SOHR Containment Isolation White Paper Report No. HI-2220845, Rev. O (Redacted) |
ML22305A511, part of ML22305A508 |
See 11/30/22 Meeting Summary |
11/01/22 |
SMR, LLC, SMR-160 GDC 40 Compliance White Paper Report No. Hl-2220836 Rev. O |
ML22305A500 |
See 11/16/22 Meeting Summary |
10/14/22 |
SMR, LLC, Hl-2220583, Rev. 1, SMR-160 I&C Architecture White Paper |
ML22287A012, part of ML22287A008 |
ML22325A343 |
10/06/22 |
Enclosure 3: HI-2220717, "SMR-160 Spent Fuel Pool Makeup White Paper" |
ML22279A006 |
See 10/18/22 Meeting Summary |
10/03/22 |
SMR, LLC Basis for Future LOCA Exemption Request for October 19, 2022 |
ML22276A070 |
See 10/19/22 Meeting Summary |
09/13/22 |
HI-2188193, Revision 1, "SMR 160 Control Rod Assembly Design Criteria Document" |
ML22271A741 |
See 09/13/22 Meeting Summary |
The prospective applicant may choose to receive NRC feedback on its White Papers during a public meeting. The NRC feedback provided during the public meeting is documented in the meeting summary.
Additional information can be obtained from ADAMS using a search by docket number 99902049.
Public Meeting Materials and Meeting Summaries for the SMR-160 Design
Future public meetings may be found through the calendar on the main NRC public site.
Additional information can be obtained from ADAMS using a search by docket number 99902049.
Correspondences related to the SMR-160 Design
The following table provides access to letters and other pre-application correspondence between SMR, LLC, a Holtec International Company, and NRC regarding the SMR (Holtec) design.
Date |
Description |
12/22/23 |
SMR, LLC Regulatory Engagement Plan, Revision 7 (Project No. 99902049) |
09/27/23 |
SMR, LLC Regulatory Engagement Plan, Revision 6 (Project No. 99902049) |
06/29/23 |
SMR, LLC, Submittal of Regulatory Engagement Plan, Revision 5 |
04/06/23 |
SMR, LLC, Submittal of Regulatory Engagement Plan, Revision 4 |
01/11/23 |
SMR, LLC Regulatory Engagement Plan, Revision 3 (Project No. 99902049) |
01/03/23 |
SMR, LLC, Online Reference Portal Information Access Agreement (Project No. 99902049) |
10/03/22 |
SMR, LLC Update to Voluntary Response to NRC Regulatory Issue Summary 2020-02 and Proposed Regulatory Engagement Plan, Revision 2 (Project No. 99902049) |
07/29/22 |
SMR, LLC Proposed Regulatory Engagement Plan, Revision 1 (Project No. 99902049) |
11/10/20 |
SMR, LLC, Submittal of Voluntary Response to NRC Regulatory Issue Summary 2020-02 |
05/07/15 |
SMR Inventec, LLC Establishment of a Safeguards Information (SGI) Program and Request for SGI Use and Storage Approval |
01/30/14 |
Voluntary Response to Regulatory Issue Summary (RIS) 2013-18 (Non-Proprietary) |
03/20/13 |
Voluntary Response to Regulatory Issue Summary (RIS) 2012-12 (Non-Proprietary) |
Clarification Questions related to the SMR-160 Design
The following table provides access to clarification questions between SMR (Holtec) and the NRC staff.
Date |
Topic |
09/05/23 |
NRC Staff Response to Questions re: Guidance for Multi-unit Probabilistic Safety Analysis (Project 99902049) |
08/14/23 |
NRC Staff Response to Questions re: Seismic Methodology (Project 99902049) |
08/10/23 |
NRC Staff response to Question re: Seismic Probabilistic Risk Assessment for a Construction Permit Application (Project 99902049) |
07/31/23 |
NRC Staff Response to Questions re: Electrical Separation for the SMR-160 design (99902049) |
07/25/23 |
NRC Staff Questions and SMR (Holtec) Responses re: July 19, 2023, Public Meeting Materials - SMR-160 Code Verification and Validation and Evaluation Methodologies (99902049) |
07/17/23 |
NRC Staff Response to Questions on IEEE 603-1991 and Completion of Protective Action (Project 99902049) |
07/10/23 |
NRC Staff Response to Questions re: Quality Assurance for the SMR-160 Design (99902049) |
06/07/23 |
Clarification Question Regarding Potential SECY Timeline Required for Potential FOAK Exemption (99902049) |
05/16/23 |
NRC Staff Response to Clarification Question re: RHR System Classification (99902049) |
03/31/23 |
NRC Staff response to Follow-up Question re: Polar Crane Analysis for the SMR-160 design (Project Number 99902049) |
03/31/23 |
NRC Staff response to Question re: Manual Initiation of Protective Action for the SMR-160 design (Project Number 99902049) |
03/10/23 |
NRC Staff Response to SMR (Holtec) Follow-up Question re: RCS Flow Instrumentation (Project 99902049) |
03/08/23 |
NRC staff response to SMR-160 question re: Polar Crane Analysis (Project 99902049) |
02/22/23 |
NRC Staff Response to SMR (Holtec) Questions re: NonSafety Structures. |
02/02/23 |
NRC Staff Response to Follow-up Questions re: Water Source for Fire Protection |
01/25/23 |
NRC Staff Response to SMR (Holtec) Questions re: Radwaste Management (RG 1.143) |
01/24/23 |
NRC Staff Response to SMR (Holtec) Question re: Wet Bulb Temperature |
01/12/23 |
NRC Staff Response to Questions regarding RG 1.99 Revision 2, Radiation Embrittlement of Reactor Vessel Materials (Project No. 99902049) |
01/05/23 |
NRC Staff Response to Follow-up Questions after the November 30 Public Meeting re: Closed Systems Isolation Valves |
01/04/23 |
NRC Staff Response to Follow-up Questions regarding the Scope of PRA and Turbine Missiles (RG 1.115) |
12/28/22 |
NRC Staff Response to Question regarding "Equivalent Materials" for the SMR-160 Design |
12/28/22 |
NRC Staff Response to Question regarding Water Source for Fire Protection |
12/19/22 |
NRC Staff Response to Clarification Question re: Reactor Coolant System Flow Instrumentation |
12/08/22 |
NRC Technical Paper re: Passive SMRs presented at IAEA Conference |
11/29/22 |
NRC Staff Response to SMR (Holtec) Clarification Question re: Aircraft Impact Assessment |
11/29/22 |
NRC Staff Response to SMR (Holtec) Clarification Question re: Turbine Missiles |
10/27/22 |
NRC Staff response to questions re: Common-Cause Failure, Common Mode-Failure, and Level/Pressure/Temperature Transmitters |
10/26/22 |
NRC Staff Response to Questions re: SECY-94-084 |
10/26/22 |
NRC Staff Response to Questions re: Aircraft Impact Analysis |
10/25/22 |
NRC Staff Response to Follow-Up Question re: CRDS (SRP 3.9.4) |
10/24/22 |
NRC Staff Response to Clarification Question regarding Codes and Standards |
10/21/22 |
NRC Staff Responses to Clarification Questions regarding Containment Stress Limits (SRP 3.9.3) |
10/17/22 |
NRC Staff Responses for Some Questions Supporting the Oct 18 SFP Public Meeting |
09/26/22 |
NRC Staff Response to the Clarification Question regarding Software for Structural Analysis |
09/09/22 |
NRC Staff Response to the Clarification Question regarding Piping Design and Analysis for the SMR-160 Design |