Date |
Description |
12/12/08 |
Summary of the Environmental Site Audit Related to the Review of the Combined License Application for Shearon Harris, Units 2 and 3 |
11/18/08 |
Environmental Scoping Summary Report |
06/11/08 |
Correction of Notice of Intent to Prepare and Environmental Impact Statement and Conduct Scoping Process |
06/04/08 |
Federal Register Notice Regarding Opportunity to Petition for Leave to Intervene |
05/25/08 |
Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Related to a Combined License for Shearon Harris Nuclear Power Plant, Units 2 and 3 |
05/16/08 |
Shearon Harris, Units 2 & 3, Combined License Application Review Schedule |
04/23/08 |
Notification of Docketing and Federal Register Notice |
03/11/08 |
Acknowledgment of Receipt of Application and Federal Register Notice |