Date |
Description |
11/07/13 |
Combined License Application (COLA) Review |
10/30/13 |
Combined License Application, Part 4, Technical Specifications, Update Tracking Report, Revision 0 |
10/30/13 |
Combined License Application, Part 2, Final Safety Analysis Report, Update Tracking Report, Revision 4 |
10/07/13 |
Combined License Application, Part 10, Update Tracking Report, Revision 4 |
08/01/13 |
Combined License Application, Part 2 Final Safety Analysis Report Revision 3 Update Tracking Report Revision 2 (Chapters 1, 2, 3, 8, 9, and 13), and ITAAC and proposed license Conditions Revision 3, Updated Tracking Report Revision 3 |
08/01/13 |
Combined License Application, Part 1, Update Tracking Report, Revision 0 |
05/13/13 |
Final Safety Analysis Report Revision 3, Update Tracking Report Revision 1 (Chapters 2, 6, 8, 9, and 19) |
03/28/13 |
Combined License Application Part 10 Revision 3 Update Tracking Report Revision 2 |
03/28/13 |
Combined License Application Part 5 Revision 3 Update Tracking Report Revision 0 |
03/28/13 |
Environmental Report Revision 3, Update Tracking Report Revision 0 (Chapters 2, 3, 4, and 6) |
03/18/13 |
Extension of regulatory commitment schedule |
02/28/13 |
Final Safety Analysis Report Revision 3, Update Tracking Report Revision 0 (Chapters 1, 2, 3, 8, 9, and 12) |
02/28/13 |
Combined License Application Part 10 Revision 3; Update Tracking report, Revision 1 |
01/28/13 |
Request for Exemption from 10 CFR 50.71(e)(3)(iii) |