Application Review Schedule for the Combined License Application for Callaway, Unit 2

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Union Electric Company (AmerenUE) submitted to obtain a combined license (COL) for an AREVA U.S. Evolutionary Power Reactor (U.S. EPR) designated as Callaway, Unit 2.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 07/24/08 - A
Acceptance Review
Acceptance Review Start
08/05/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
12/12/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
 
Safety Review
Phase A - Requests for Additional Information (RAIs) Issued to Applicant
Suspended
Phase B - Advanced Final Safety Evaluation Report (SER) without Open Items
Suspended
Phase C - ACRS Review of Advanced Final SER
Suspended
Phase D - Final SER
Suspended
Environmental Review
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
Suspended
Phase 2 - Draft EIS issued to EPA
Suspended
Phase 3 - Response to public comments on draft EIS issued
Suspended
Phase 4 - Final EIS issued to EPA
Suspended
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.