United States Nuclear Regulatory Commission - Protecting People and the Environment
Home > Nuclear Materials > Uranium Recovery > License Applications > Ludeman > Application Review Schedule

Application Review Schedule for Ludeman

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Uranium One submitted to obtain a license for its Ludeman In Situ Recovery site.

Key Milestones Completion Date
Actual - A
Target - T
Application Received 12/06/11
License Application in ADAMS 01/03/12 – A
Acknowledgement email Sent (11 days from receipt) 12/19/11 – A
Acceptance Review
Application accepted for review
05/06/12 – A
Acceptance Review Complete (60 days from Acceptance Review Begins)
05/16/12 – A
Safety Review
Safety RAIs issued
01/15/13 – A
Licensee submits major "change of design" request deferring amended application submission for RAI response revisions
03/13/13 – A
RAIs responses received in full
03/13/14 – A
Second round of Targeted RAIs submitted sent
12/01/14 – A
Targeted RAI responses received
06/08/15 – A
Revised Application (Technical Report) including "Change of Design" modification received
06/30/17 – A
Final SER Complete
03/01/18 – A
Environmental Review
Requests for RAIs to Applicant
01/19/13 – A
RAI responses received in full
03/13/14 – A
Draft Environmental Assessment (EA) issued
02/27/18* – A
Final EA Issued
08/03/18** – T
Issue License Amendment 08/31/18 – T

*Based on August 31, 2017 submittal of revised Environmental Report
**Issuance of the Final EA is contingent upon completion of the National Historic Preservation Act (NHPA) Section 106 consultation

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

To top of page

Page Last Reviewed/Updated Monday, March 12, 2018