Partial response to FOIA request for documents re status of plants readiness for OL,IE Manual,Chapter 94300.Apps A & B documents available in PDR & encl.App C documents partially & completely withheld (ref FOIA Exemption 5).
Accession Number: ML20234D050
Date Released: Saturday, September 5, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20234D048 - Partial response to FOIA request for documents re status of plants readiness for OL,IE Manual,Chapter 94300.Apps A & B documents available in PDR & encl.App C documents partially & completely withheld (ref FOIA Exemption 5). (6 page(s), 6/30/1987)
- ML20234D136 - Forwards rept on status of facility completion,per Insp Procedure 94300B.Projected fuel load is 850415.All sys not turned over & question remains whether testing or as-buit verification will be critical path.Updates will be provided. (12 page(s), 3/22/1985)
- ML20234D229 - Forwards Rev 3 to status of facility completion rept,per Insp Procedure 94300B.Licensee projected fuel load date is July 1985.Reasons for schedule change include clearing of items on licensee master punch list & completion of testing. (53 page(s), 6/19/1985)
- ML20234D160 - Forwards status of facility completion rept,Rev 1,per Insp Procedure 94300B.Licensee projected fuel load date changed to June 1985 from Apr 1985,as result of slippage in test completion schedule.Rept to be updated as required. (14 page(s), 4/22/1985)
- ML20234D528 - Comments on comparison of as-built plant w/facility Tech Specs.Details of review to be reflected in Insp Rept 50-529/85-44 & IE Insp Procedure 71301, "Tech Spec Review," dtd 850322.Proposed Tech Specs clear & enforceable. (1 page(s), 11/27/1985)
- ML20234D395 - Submits work items & schedule for completion of security communications deficiency from preoperational physical security insps on 851003-10 & 1111-14,including replacement of coaxial wire to bldg radio antennas by 860215. (2 page(s), 11/14/1985)
- ML20234D289 - Requests info,identified in Attachment 1,documenting const status & readiness for operation of facility.Rept used by NRC mgt & Commission to evaluate near-term OL facility.Info requested within 15 days of ltr date. (6 page(s), 10/10/1985)
- ML20234D186 - Forwards Rev 2 to status of facility completion rept,per Insp Procedure 94300B.Licensee projected fuel load date is June 1985.Violations,deviations & open items resulting from insps must be resolved prior to fuel load. (24 page(s), 5/21/1985)
- ML20234D348 - Forwards proof & review comments re Tech Specs for facility. Licensee should test emergency lighting sys & demonstrate operability prior to initial entry into Mode 2 & replace coaxial wiring to security radio antennas in radwaste bldgs. (4 page(s), 11/4/1985)
- ML20234D607 - Provides info on preparedness for full power licensing. Licensee estimates initial criticality date of 860322 w/ completion of low power testing few days later.Region V considers time frame realistic for full power licensing. (8 page(s), 3/5/1986)
- ML20235A303 - Forwards Rev 4 to status of facility completion rept,per Insp Procedure 94300B.Util projected fuel load date is Jul 1985.Date may require rev due to clearing of items on util master list & completion of sys & bldg turnover. (13 page(s), 7/22/1985)