Event Notification Report for May 1, 2015

U.S. Nuclear Regulatory Commission
Operations Center

Event Reports For
04/30/2015 - 05/01/2015

** EVENT NUMBERS **

 
50998 51007 51026 51027

To top of page
Power Reactor Event Number: 50998
Facility: HATCH
Region: 2 State: GA
Unit: [1] [2] [ ]
RX Type: [1] GE-4,[2] GE-4
NRC Notified By: STEVE BRUNSON
HQ OPS Officer: CHARLES TEAL
Notification Date: 04/20/2015
Notification Time: 21:26 [ET]
Event Date: 08/07/2014
Event Time: 17:07 [EDT]
Last Update Date: 04/30/2015
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(ii)(B) - UNANALYZED CONDITION
Person (Organization):
ALAN BLAMEY (R2DO)
 
Unit SCRAM Code RX CRIT Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
2 N Y 90 Power Operation 90 Power Operation

Event Text

THIS IS A CONTINUATION OF EN #50351

* * * UPDATE FROM STEVE BRUNSON TO CHARLES TEAL ON 4/20/15 AT 2126 EDT * * *

"During an expanded scope inspection, deficiencies in the following areas were observed that caused the affected barriers to be considered nonfunctional:

- A gap ¬" wide, 1" tall, and 6" deep was found at penetration 1Z43H594D on the west wall of the U1 East Cableway (separating Fire Area 1104 and Fire Area 1020)

- Near penetration 1Z43J837D, and approximately 12" south and above 1Z43H837D, gaps were observed in the mortar joint between CMU on the west wall of the U1 East Cableway (separating Fire Area 1104 and Fire Area 1020)

- A triangular gap 1" wide, 1" tall and 6" deep was found at penetration 1Z43H592D on the west wall of the U1 East Cableway (separating Fire Area 1104 and Fire Area 1020)

- A gap 4" tall and 3" wide was found behind Turn Box TB1-1272 which covers penetrations 1Z43H590D, 1Z43H589D, 1Z43H588, and 1Z43H587D on the west wall of the U1 East Cableway (separating Fire Area 1104 and Fire Area 1020)

- At the architectural joint between the vertical wall to the horizontal floor/ceiling assembly above door 1C-22, above and to the south of 1Z43H1105D, a gap was observed approximately ¬" tall, 3" wide, and 6" deep on the west wall of the U1 East Cableway Foyer (separating Fire Area 1105 and Fire Area 0014K)

- Gap between the grout and the conduit of penetration 1Z43H778D approximately ¬" tall x 1.5" wide x 6" deep on the east wall of the Unit 1 130' Elevation Control Building Working Floor Hallway (separating Fire Area 0014K and Fire Area 1105)

"The nonconforming conditions observed for the affected fire penetrations and fire barriers were identified as affecting both safe shutdown paths for Unit 2. Compensatory measures were already in place in accordance with the plant's Fire Hazard Analysis (FHA) as a result of previous conditions involving degraded barriers in the same fire areas and will remain in place until the fire barriers are repaired. The presence of the compensatory measures in addition to portable fire protection equipment located in adjacent areas ensure the safe shutdown paths are preserved until the degraded conditions are repaired.

"CR 10058276; CR 10058278

"The following deficiencies were also observed causing the affected penetrations to be considered nonfunctional:

- A gap ¬" wide, 1" tall, and 6" deep was located at penetration 1Z43H532D on the west wall of the U1 East Cableway (separating Fire Area 1104 and Fire Area 0014M)

- A gap 1/8" wide, 1" tall and 6" deep was located at penetration 1Z43H780D on the west wall of the U1 East Cableway (separating Fire Area 1104 and Fire 0014M)

- A gap ¬" wide, 1" tall, and 6" deep was located at penetration 1Z43H781D on the west wall of the U1 East Cableway (separating Fire Area 1104 and Fire 0014M). A ¬" x «" defect was also identified at penetration 1Z43H781D on the east wall of the Men's Restroom in the Control Building (separating Fire Area 0014M and Fire Area 1104)

"The nonconforming conditions observed for the affected penetrations were identified as affecting both safe shutdown paths for Unit 1 and Unit 2. Compensatory measures were already in place in accordance with the plant's Fire Hazard Analysis (FHA) as a result of previous conditions involving degraded barriers in the same fire areas and will remain in place until the fire barriers are repaired. The presence of compensatory measures in addition to portable fire protection equipment located in adjacent areas ensures the safe shutdown paths are preserved until degraded conditions are repaired.

"CR 10058277

"The expanded scope inspection activity is continuing and this and any subsequent similar condition(s) that meets the reporting requirements will be included in an ENS Update Report as required and will be documented in a revised LER at the end of the inspection activity."

The licensee has notified the NRC Resident Inspector. Notified R2DO (Blamey).

* * * UPDATE FROM SCOTT BRITT TO DONG PARK ON 4/23/15 AT 1654 EDT * * *

"During an expanded scope inspection, deficiencies in the following areas were observed that caused the affected barriers to be considered nonfunctional:

- A gap 1/4" wide, 1" tall and 7" deep was found at penetration 1Z43H1138D on the east wall of the U1 RPS MG Set Room (separating Fire Area 1013 and Fire Area 0040). No seal material was seen between the sleeve and the cinderblock on the north side of penetration.

- A void 1" tall, 1" wide, and 7" deep was found in the south upper corner under a concrete beam at column line T12 above penetration 1Z43H941D on the east wall of the U1 RPS MG Set Room (separating Fire Area 1013 and Fire Area 0040).

- At penetration 1Z43H1139D, it appears that combustible neoprene insulation is used around the pipe within the plane of the west wall of the Vertical Cable Chase Room (separating Fire Area 0040 and Fire Area 1013). Combustible materials would not be part of a rated pen seal.

- A gap 1" wide, 1" tall and 7" deep was observed at penetration 1Z43H1138D on the west wall of the Vertical Cable Chase Room (separating Fire Area 0040 and Fire Area 1013).

"The nonconforming conditions observed for the affected fire penetrations and fire barriers were identified as affecting both safe shutdown paths for Unit 1. Compensatory measures were already in place in accordance with the plant's Fire Hazard Analysis (FHA) as a result of previous conditions involving degraded barriers in the same fire areas and will remain in place until the fire barriers are repaired. The presence of the compensatory measures in addition to portable fire protection equipment located in adjacent areas ensures the safe shutdown paths are preserved until the degraded conditions are repaired. The expanded scope inspection activity is continuing, and this and any subsequent similar condition(s) that meets the reporting requirements will be included in an ENS Update Report as required and will be documented in a revised LER at the end of the inspection activity.

"CR 10060228"

The licensee will notify the NRC Resident Inspector. Notified R2DO (Blamey).

* * * UPDATE FROM STANLEY STONE TO DONG PARK ON 4/27/15 AT 2047 EDT * * *

"During an expanded scope inspection, deficiencies in the following areas were observed that caused the affected barriers to be considered nonfunctional:

-An opening in the grout 1/4" wide, 1/2" tall and over 7" deep was found between the wall and the outside sleeve for penetration 2Z43H028D on the west wall of the U2 Transformer Room (separating Fire Area 2019 and Fire Area 2016).

-A 1/4" diameter hole in the grout approximately 2.5" deep was found above conduit 2MI2128 on the west wall of the U2 Transformer Room (separating Fire Area 2019 and Fire Area 2016).

"The nonconforming conditions observed for the affected penetration and fire barrier were identified as affecting both safe shutdown paths for Unit 1 and Unit 2. Compensatory measures were already in place in accordance with the plant's Fire Hazard Analysis (FHA) as a result of previous conditions involving degraded barriers in the same fire areas and will remain in place until the fire barriers are repaired. The presence of the compensatory measures in addition to portable fire protection equipment located in adjacent areas ensures the safe shutdown paths are preserved until the degraded conditions are repaired. The expanded scope inspection activity is continuing, and this and any subsequent similar condition(s) that meets the reporting requirements will be included in an ENS Update Report as required and will be documented in a revised LER at the end of the inspection activity.

"CR 10061830"

The licensee notified the NRC Resident Inspector. Notified R2DO (Blamey).


* * * UPDATE FROM PAUL UNDERWOOD TO DONG PARK ON 4/28/15 AT 1640 EDT * * *

"During an expanded scope inspection, deficiencies in the following areas were observed that caused the affected barriers in the Unit 2 Control Building 130' elevation to be considered nonfunctional and represented degraded conditions of penetrations through the wall separating the Unit 2 Switchgear Access Hallway - Fire Area 2014, from the U2 West 600 V Switchgear Room - Fire Area 2016.

"The following conditions were located on the south wall of the Unit 2 Switchgear Access Hallway (Fire Area 2014).

1. An opening between the conduit and the wall 1/4" wide, 2" long and probed to be at least 2 1/2" deep was identified for penetration 2Z43H668D. A similar condition exists for this penetration on the opposite side of the wall in Fire Area 2016.
2. An opening between the conduit and the wall 1/4" wide, 1/2" long and probed to be at least 3" deep was identified for penetration 2Z43H667D. A similar condition exists for this penetration on the opposite side of the wall in Fire Area 2016.

The following conditions were located on the opposite side of the same wall. This is the north wall of the U2 West 600V Switchgear Room (Fire Area 2016):
3. An opening between the conduit and the wall 1/8" wide, 1" long and probed to be at least 4" deep was identified for penetration 2Z43H668D.
4. An opening between the conduit and the wall 1/8" wide, 1" long and probed to be at least 3" deep was identified for penetration 2Z43H667D.
5. An opening between the conduit and the wall 2 1/2" wide, 2 1/2" long and probed to be at least 4" deep was identified around the 2" continuous run conduit located above cable tray penetration 2Z43H031D.
6. An opening between the conduit and the wall 1/4" wide, 3/4" long and probed to be at least 6" deep was identified above a 3/4" continuous run conduit (first of three) located at the ceiling near column line TE.
7. An opening between the conduit and the wall 1/4" wide, 1/2" long and probed to be at least 6" deep was identified above a 3/4" continuous run conduit (second of three) located at the ceiling near column line TE.
8. An opening between the conduit and the wall 1/4" wide, 3/4" long and probed to be at least 5" deep was identified above a 3/4" continuous run conduit (third of three) located at the ceiling near column line TE.

"The nonconforming conditions observed for the affected penetration and fire barrier were identified as affecting both safe shutdown paths for Unit 2. Compensatory measures were already in place in accordance with the plant's Fire Hazard Analysis (FHA) as a result of previous conditions involving degraded barriers in the same fire areas and will remain in place until the fire barriers are repaired. The presence of the compensatory measures in addition to portable fire protection equipment located in adjacent areas ensures the safe shutdown paths are preserved until the degraded conditions are repaired. The expanded scope inspection activity is continuing, and this and any subsequent similar condition(s) that meets the reporting requirements will be included in an ENS Update Report as required and will be documented in a revised LER at the end of the inspection activity.

"CR 10062254"

The licensee notified the NRC Resident Inspector. Notified R2DO (Ehrhardt).

* * * UPDATE FROM PAUL UNDERWOOD TO DANIEL MILLS ON 4/29/15 AT 1804 EDT * * *

"During an expanded scope inspection, deficiencies in the Unit 2 Control Building 130 foot elevation were observed that caused the affected barriers to be considered nonfunctional and represented degraded conditions of penetrations through the wall separating the Unit 2 West DC Switchgear Room 2A (Fire Area 2018) and the Unit 2 Switchgear Access Hallway (Fire Area 2014).

"The following conditions were located on the west wall of the Unit 2 Switchgear Access Hallway (Fire Area 2014).
1. An opening between the conduit and the wall ¬ inch wide, 1 inch long and probed to be greater than 2 inch deep, was identified for penetration 2Z43H673D.
2. There is insufficient masonry material to fill the full depth of the wall above the ductwork that passes through penetration 2Z43H032D. This deficiency affects a small area on the south side of the ductwork and penetrations 2Z43H789D, 2Z43H790D, and 2Z43H791D.
3. An opening between the conduit and the wall ¬ inch wide, 1 inch long and probed to be 4 inch deep was identified for penetration 2Z43H671D. A similar condition exists for this penetration on the opposite side of the wall (see Item 5 below).

"The following conditions were located on the east wall of the Unit 2 West DC Switchgear Room 2A (Fire Area 2018).
4. There are openings between the conduits and the wall «  inch wide and 1 inch long for penetrations 2Z43H789D, 2Z43H790D, and 2Z43H791D. These penetrations are affected in Item 2 above.
5. An opening between the conduit and the wall 1 inch wide, 1 inch long and probed to be greater than 6 inch deep, was identified for penetration 2Z43H671D.
6. An opening between the conduit and the wall ¬ inch wide, 1 inch long and probed to be at least 2 inch deep, was identified for penetration 2Z43H673D.
7. An opening between the conduit and the wall ¬ inch wide, 1 inch long and probed to be at least 2 «  inch deep, was identified for penetration 2Z43H676D.

"The nonconforming conditions observed for the affected penetrations were identified as affecting both safe shutdown paths for Unit 2. Compensatory measures were already in place in accordance with the plant's Fire Hazard Analysis (FHA) as a result of previous conditions involving degraded barriers in the same fire areas and will remain in place until the fire barriers are repaired. The presence of the compensatory measures in addition to portable fire protection equipment located in adjacent areas ensures the safe shutdown paths are preserved until the degraded conditions are repaired. The expanded scope inspection activity is continuing, and this and any subsequent similar condition(s) that meets the reporting requirements will be included in an ENS Update Report as required and will be documented in a revised LER at the end of the inspection activity.

"CR10062955"

The licensee notified the NRC Resident Inspector. Notified R2DO (Ehrhardt).

* * * UPDATE FROM JOHN MITCHELL TO HOWIE CROUCH AT 2137 EDT * * *

"During an expanded scope inspection, deficiencies in the Control Building 130' elevation were observed that caused the affected barriers to be considered nonfunctional and represented degraded conditions of the following penetrations through the wall separating the Unit 2 East Cableway (Fire Area 2104) and the Health Physics Hallway and Counting Room (Fire Areas 0014B and 0014G).
- Penetration 2Z43H783D terminates open within a foot of the east wall of the Health Physics Counting Room (Fire Area 0014G)
- Penetration 2Z43H603D contains no visible seal material and is located on the east wall of the Health Physics Hallway (Fire Area 0014B).

"The nonconforming conditions observed for the affected penetrations were identified as affecting both safe shutdown paths for Unit 1 and Unit 2.

"Deficiencies were also observed that caused the affected barriers to be considered nonfunctional and represented degraded condition of the wall separating the Unit 2 East Cableway (Fire Area 2104) from the common East Cableway Foyer (Fire Area 1105).
- Gap near penetration 2Z43H170D between a conduit and the concrete masonry unit (CMU) wall located on the south wall of the Unit 2 East Cableway (Fire Area 2104).

"The nonconforming conditions observed for the affected fire barriers were identified as affecting both safe shutdown paths for Unit 1.

"Compensatory measures were already in place in accordance with the plant's Fire Hazard Analysis (FHA) as a result of previous conditions involving degraded barriers in the same fire areas but were modified based on the nature of the degradations noted in the condition report and will remain in place until the fire barriers are repaired. The presence of the compensatory measures in addition to portable fire protection equipment located in adjacent areas ensures the safe shutdown paths are preserved until the degraded conditions are repaired. The expanded scope inspection activity is continuing, and this and any subsequent similar condition(s) that meets the reporting requirements will be included in an ENS Update Report as required and will be documented in a revised LER at the end of the inspection activity.

"CR10063642"

Notified R2DO (Ehrhardt).

To top of page
Agreement State Event Number: 51007
Rep Org: TEXAS DEPT OF STATE HEALTH SERVICES
Licensee: RRC POWER AND ENERGY LLC
Region: 4
City: ROUND ROCK State: TX
County:
License #: 06105
Agreement: Y
Docket:
NRC Notified By: ART TUCKER
HQ OPS Officer: JEFF ROTTON
Notification Date: 04/23/2015
Notification Time: 23:13 [ET]
Event Date: 04/23/2015
Event Time: 20:45 [CDT]
Last Update Date: 04/24/2015
Emergency Class: NON EMERGENCY
10 CFR Section:
AGREEMENT STATE
Person (Organization):
JAMES DRAKE (R4DO)
NMSS_EVENTS_NOTIFICA (EMAI)
ILTAB (EMAI)
MEXICO (EMAI)
 
This material event contains a "Less than Cat 3 " level of radioactive material.

Event Text

AGREEMENT STATE REPORT - LOST MOISTURE DENSITY GAUGE

The following information was provided by the State of Texas via email:

"On April 23, 2015, at 2117 [CDT], the Agency [Texas Department of State Health Services] was contacted by the licensee's radiation safety officer (RSO) and informed that one of their InstroTek model 3500 moisture/density gauges containing an 8 millicurie cesium - 137 source and a 40 millicurie americium/beryllium source was lost by a technician at a work site [Midland, Texas]. The technician had placed the gauge on the back of his pickup truck. He walked around the job site with the work area supervisor for a few minutes, then returned to his truck and drove to the new work site. When he arrived at the new site he notice the gauge was missing. The technician notified the RSO and local law enforcement. He then began looking for the gauge. The RSO stated he was responding to the location to help look for the gauge. The RSO stated the operating rod for the cesium source was locked in the shielded position. Additional information will be provided as it is received in accordance with SA-300."

Texas Incident #: I-9307

* * * UPDATE ON 4/24/15 AT 1508 EDT FROM ART TUCKER TO DONG PARK * * *

The following information was provided by the State of Texas via email:

"On April 24, 2015, at 0929 CDT the Agency [Texas Department of State Health Services] was notified by the licensee's radiation safety officer (RSO) that the gauge had been recovered. The RSO stated they had been contacted by a contractor who had found the gauge yesterday and taken it to their [location] where they stored it over night. The RSO stated the operating handle for the cesium source was still locked. The gauge did not appear to be damaged. The RSO stated a leak test was performed of the gauge sources and the gauge has been placed in storage until the results of the leak test are received. Additional information will be provided as it is received in accordance with SA-300."

Notified R4DO (Drake), NMSS Events Notifications, ILTAB, and Mexico via email.


THIS MATERIAL EVENT CONTAINS A "LESS THAN CAT 3" LEVEL OF RADIOACTIVE MATERIAL

Sources that are "Less than IAEA Category 3 sources," are either sources that are very unlikely to cause permanent injury to individuals or contain a very small amount of radioactive material that would not cause any permanent injury. Some of these sources, such as moisture density gauges or thickness gauges that are Category 4, the amount of unshielded radioactive material, if not safely managed or securely protected, could possibly - although it is unlikely - temporarily injure someone who handled it or were otherwise in contact with it, or who were close to it for a period of many weeks. For additional information go to http://www-pub.iaea.org/MTCD/publications/PDF/Pub1227_web.pdf

To top of page
Power Reactor Event Number: 51026
Facility: OCONEE
Region: 2 State: SC
Unit: [1] [ ] [ ]
RX Type: [1] B&W-L-LP,[2] B&W-L-LP,[3] B&W-L-LP
NRC Notified By: JERRY COLLIER
HQ OPS Officer: DANIEL MILLS
Notification Date: 04/30/2015
Notification Time: 19:38 [ET]
Event Date: 04/30/2015
Event Time: 18:40 [EDT]
Last Update Date: 04/30/2015
Emergency Class: UNUSUAL EVENT
10 CFR Section:
50.72(a) (1) (i) - EMERGENCY DECLARED
Person (Organization):
FRANK EHRHARDT (R2DO)
BERNARD STAPLETON (IRD)
SCOTT MORRIS (NRR)
BILL DEAN (ET)
VICTOR MCCREE (RA)
 
Unit SCRAM Code RX CRIT Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 99 Power Operation

Event Text

UNUSUAL EVENT DECLARED DUE TO ELECTRICAL FAULT

"Unusual Event (4.6.U.1) was declared by the Shift Manager at Oconee Nuclear Station at 1840 EDT on 4/30/15 due to scorched 4160V cable and a hole created in metal connector coming into the top of 1C condensate booster pump motor electrical junction box. Unit 1 experienced a decrease in power to approximately 98.6% power due to the perturbation in condensate flow from the loss of 1C condensate booster pump. Unit 1 is currently stable at 98.6%. 1A condensate booster pump auto-started as expected. Smoke was observed and quickly dissipated. No visible fire or flame was observed. No Fire Brigade response required."

The Unusual Event was terminated at 1945 EDT on 4/30/15.

The licensee informed state/local agencies and the NRC Resident Inspector and does not plan to issue a press release.

Notified other Federal Agencies (DHS SWO, FEMA Ops, FEMA NWC, NICC Watch Officer and NuclearSSA).

To top of page
Power Reactor Event Number: 51027
Facility: COLUMBIA GENERATING STATION
Region: 4 State: WA
Unit: [2] [ ] [ ]
RX Type: [2] GE-5
NRC Notified By: EDAN ENGSTROM
HQ OPS Officer: DANIEL MILLS
Notification Date: 04/30/2015
Notification Time: 21:24 [ET]
Event Date: 04/29/2015
Event Time: 18:11 [PDT]
Last Update Date: 04/30/2015
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
Person (Organization):
GEOFFREY MILLER (R4DO)
 
Unit SCRAM Code RX CRIT Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 95 Power Operation 95 Power Operation

Event Text

ROD POSITION INDICATOR SYSTEM (RPIS) UNPLANNED OUTAGE

"At 1811 PDT on 04/29/2015, the station declared the RPIS system inoperable when a Control Room panel alarmed the loss of indication. The cause of the equipment loss is under investigation. This unplanned equipment outage is being conservatively reported as a major loss of assessment capability in accordance with 10 CFR 50.72(b)(3)(xiii).

"No other safety equipment has been impacted by this event and the plant continues normal operation."

The NRC Resident Inspector has been notified.

Page Last Reviewed/Updated Thursday, March 25, 2021