United States Nuclear Regulatory Commission - Protecting People and the Environment

Resolution of Generic Safety Issues: Issue 5: Design Check and Audit of Balance-of-Plant Equipment ( NUREG-0933, Main Report with Supplements 1–34 )

DESCRIPTION

The concern of this issue involves the requirement for verification that the balance-of-plant equipment satisfies the design intent. This issue was identified in NUREG-0705.44

CONCLUSION

Task I.F in NUREG-0660,48 the TMI Action Plan, is a task to expand the QA list. Issue 5 is a portion of the TMI task and, therefore, will be prioritized in conjunction with TMI Action Plan Item I.F.1 in Section 3 of this report.

Page Last Reviewed/Updated Thursday, March 29, 2012