Home > NRC Library > Document Collections > General Communications > Information Notices > 1992 > IN 92-07
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D.C. 20555
January 9, 1992
NRC INFORMATION NOTICE 92-07: RAPID FLOW-INDUCED EROSION/CORROSION
OF FEEDWATER PIPING
Addressees
All holders of operating licenses or construction permits for pressurized
water reactors.
Purpose
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information
notice to alert addressees to problems discovered at the Catawba Nuclear
Station, Unit 2, involving the rapid flow-induced erosion/corrosion of
feedwater piping. The problem discovered at Catawba affects the piping
supplying the upper feedwater nozzles and may apply to all Westinghouse
units employing steam generator models D-4, D-5, and E, in which a portion
of main feedwater is diverted to the upper feedwater nozzles when the unit
is operating. It is expected that recipients will review the information
for applicability to their facilities and consider actions, as appropriate,
to avoid similar problems. However, suggestions contained in this
information notice are not NRC requirements; therefore, no specific action
or written response is required.
Description of Circumstances
On November 4, 1991, while performing ultrasonic testing on a section of
4-inch feedwater system piping on Catawba's Unit 2 A steam generator, the
licensee, Duke Power Company, detected several locations that were at or
near minimum acceptable wall thickness. The licensee detected similar
results on the other three steam generators. The licensee was performing
this testing as part of its prescribed piping erosion/corrosion control
program.
The licensee removed sections of the A106B carbon steel piping for analysis
or replacement. This analysis revealed that the piping had undergone
significant, symmetric, flow-induced, single phase erosion/corrosion. In
some areas, the 4-inch schedule 80 pipe (nominal thickness 0.337 inch) had
been thinned to 0.185 inch in only four operating cycles. This implies an
erosion/corrosion rate of approximately 0.040 inch per cycle. The licensee
identified approximately 90 feet of affected pipe for replacement.
It appears that the thinning is directly attributable to the design of the
steam generators (Model D5) on Catawba Unit 2, which requires a split-flow
feedwater delivery system. In this design, typically 10-20 percent of the
total feedwater flow is delivered to the upper feedwater nozzles to prevent
9201090188
.
IN 92-07
January 9, 1992
Page 2 of 2
flow-induced vibration damage to the steam generator feedwater preheater
section when full feedwater flow is delivered through the main nozzles.
The original Catawba feedwater system design did not employ split-flow
delivery at power. As a result, the piping was not sized to accommodate the
operating flow rates, resulting in flow velocities of 30-35 feet per second
in sections of 4-inch piping. This high flow rate has led to rapid
erosion/corrosion. In the case of Catawba, Unit 2, if the subject piping in
the feedwater preheater bypass line had ruptured, the break would not have
been isolable and would have resulted in the steam generator fluid being
released outside containment.
This problem applies to Westinghouse units employing steam generator models
D-4, D-5, and E if the flow reaches a high velocity when a portion of normal
feedwater is diverted to the upper feedwater nozzles. In numerous generic
communications, the staff has previously stated that high velocity flows may
cause rapid flow-induced erosion/corrosion in carbon steel piping.
This information notice requires no specific action or written response. If
you have any questions about the information in this notice, please contact
one of the technical contacts listed below or the appropriate Office of
Nuclear Reactor Regulation (NRR) project manager.
Charles E. Rossi, Director
Division of Operational Events Assessment
Office of Nuclear Reactor Regulation
Technical contacts: William Orders, RII
(803) 831-2963
John Zeiler, RII
(803) 831-2963
Krysztof I. Parczewski, NRR
(301) 504-2705
Attachment: List of Recently Issued NRC Information Notices
.
Page Last Reviewed/Updated Thursday, March 29, 2012

