Power Reactor Status Report for November 09, 2012

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 100
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 88 INCREASING POWER *
Ginna 0 2012-10-21 REFUELING OUTAGE
Hope Creek 1 100
Indian Point 2 100 138 KV FEEDER (LINE 13332) OOS
Indian Point 3 100 138 KV FEEDER (LINE 13332) OOS
Limerick 1 100
Limerick 2 100
Millstone 2 0 2012-10-06 REFUELING OUTAGE
Millstone 3 100
Nine Mile Point 1 30 HOLDING POWER- TURBINE VIBRATION EVALUATION *
Nine Mile Point 2 100
Oyster Creek 0 2012-10-21 REFUELING OUTAGE
Peach Bottom 2 100
Peach Bottom 3 100
Pilgrim 1 100
Salem 1 100
Salem 2 0 2012-10-14 REFUELING OUTAGE
Seabrook 1 100
Susquehanna 1 81 INCREASING POWER *
Susquehanna 2 0 2012-11-08 MANUAL SCRAM. SEE EN#48496 *
Three Mile Island 1 100
Vermont Yankee 88 INCREASING POWER TO 100% FOLLOWING ROD PATTERN ADJUSTMENT *

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 0 2012-10-19 REFUELING OUTAGE
Browns Ferry 2 100
Browns Ferry 3 95 INCREASING POWER FOLLOWING EXCTRACTION STEAM LINEUP CHANGE *
Brunswick 1 100 *
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Crystal River 3 0 2009-09-25 DEFUELED - CONT.TENSIONING ON HOLD
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 100
Hatch 2 100
McGuire 1 100
McGuire 2 0 2012-09-15 MAINTENANCE OUTAGE
North Anna 1 100
North Anna 2 99 INCREASING POWER *
Oconee 1 0 2012-10-26 DEFUELED
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 0 2012-08-05 REFUELING OUTAGE *
Sequoyah 1 100
Sequoyah 2 0 2012-10-14 DEFUELED
Summer 0 2012-10-12 DEFUELED
Surry 1 100
Surry 2 0 2012-10-31 REFUELING OUTAGE
Turkey Point 3 98 HOLDING POWER FOR EPU TESTING
Turkey Point 4 0 2012-11-04 REFUELING OUTAGE
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 46 INCREASING POWER TO 100% *
Byron 1 100
Byron 2 100
Clinton 97 100% ELECTRICAL CAPABILITY
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 99 REDUCED POWER DUE TO PROBLEM WITH PLANT COMPUTER *
Dresden 2 100
Dresden 3 95 COASTDOWN TO REFUELING OUTAGE - SCHEDULED FOR 11/12 *
Duane Arnold 0 2012-10-05 REFUELING OUTAGE
Fermi 2 0 2012-11-07 FORCED OUTAGE - SEE EN#48487 *
Kewaunee 100
La Salle 1 100
La Salle 2 100
Monticello 100
Palisades 100 *
Perry 1 100
Point Beach 1 100
Point Beach 2 0 2012-10-31 REFUELING OUTAGE
Prairie Island 1 0 2012-10-22 REFUELING OUTAGE
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 0 2012-11-01 RCP MOTOR WORK COMPLETED - RCP STARTUP IN PROGRESS *
Comanche Peak 2 52 HOLDING POWER TO REPAIR SOURCE OF SODIUM LEAKAGE IN THE "2A" AUX CONDENSER *
Cooper 0 2012-10-13 REFUELING OUTAGE
Diablo Canyon 1 100
Diablo Canyon 2 100
Fort Calhoun 0 2011-04-09 DEFUELED
Grand Gulf 1 93 HOLDING POWER WHILE VERIFYING SEAL OIL SYSTEM *
Palo Verde 1 100
Palo Verde 2 2 INCREASING POWER *
Palo Verde 3 100
River Bend 1 100
San Onofre 2 0 2012-01-09 REFUELING OUTAGE - SWITCHYARD RESTRICTIONS BUT NO GRID RESTRICTIONS
San Onofre 3 0 2012-01-31 FORCED OUTAGE - S/G REPAIR - DEFUELED - SWITCHYARD RESTRICTIONS BUT NO GRID RESTRICTIONS
South Texas 1 0 2012-10-20 DEFUELED
South Texas 2 100
Waterford 3 0 2012-10-17 DEFUELED
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.