Power Reactor Status Report for April 5, 2007

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 65   HOLDING POWER FOR MAIN FEED PUMP WORK *  
FitzPatrick 100        
Ginna 100        
Hope Creek 1 100        
Indian Point 2 100        
Indian Point 3 81   INCREASING POWER *  
Limerick 1 100        
Limerick 2 44   INCREASING POWER *  
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 0 03/16/2007 REFUELING OUTAGE AND 345KV BKR OOS FOR MAINTENANCE    
Nine Mile Point 2 100        
Oyster Creek 100        
Peach Bottom 2 100        
Peach Bottom 3 100        
Pilgrim 1 81   COASTDOWN TO REFUELING OUTAGE *  
Salem 1 0 03/27/2007 DEFUELED *  
Salem 2 100        
Seabrook 1 100   369 KV NEWINGTON LINE OOS    
Susquehanna 1 100        
Susquehanna 2 0 03/03/2007 REFUELING OUTAGE    
Three Mile Island 1 100        
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 03/03/1985 500 KV (MADISON) LINES OOS    
Browns Ferry 2 0 02/20/2007 REFUELING OUTAGE 500 KV (MADISON) LINES OOS    
Browns Ferry 3 100   500 KV (MADISON) LINES OOS    
Brunswick 1 0 04/01/2007 PREPARING FOR STARTUP *  
Brunswick 2 0 03/02/2007 REFUELING OUTAGE    
Catawba 1 100        
Catawba 2 100        
Crystal River 3 100        
Farley 1 90   INCREASING POWER AFTER COMPLETING UNPLANNED MAINTENANCE *  
Farley 2 90   COASTDOWN TO REFUELING OUTAGE *  
Harris 1 100        
Hatch 1 100        
Hatch 2 100        
McGuire 1 0 03/10/2007 DEFUELED    
McGuire 2 100        
North Anna 1 100        
North Anna 2 0 03/17/2007 RELOAD IN PROGRESS *  
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 88   COASTDOWN TO REFUELING OUTAGE *  
Saint Lucie 1 0 04/01/2007 REFUELING OUTAGE    
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 100        
Summer 100        
Surry 1 100        
Surry 2 100        
Turkey Point 3 100        
Turkey Point 4 100        
Vogtle 1 98   100% ELECTRICAL CAPABILITY. *  
Vogtle 2 0 03/03/2007 DEFUELED    
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 0 04/01/2007 REFUELING OUTAGE    
Clinton 97   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100        
D.C. Cook 2 100        
Davis-Besse 100        
Dresden 2 98   100% ELECTRICAL CAPABILITY    
Dresden 3 99   100% ELECTRICAL CAPABILITY    
Duane Arnold 5   NORMAL REACTOR STARTUP IN PROGRESS *  
Fermi 2 100        
Kewaunee 100        
La Salle 1 100        
La Salle 2 100        
Monticello 0 03/13/2007 REFUELING OUTAGE    
Palisades 100        
Perry 1 0 04/01/2007 REFUELING OUTAGE *  
Point Beach 1 0 03/31/2007 REFUELING OUTAGE    
Point Beach 2 100        
Prairie Island 1 100   345 KV OFFSITE PWR LINE OOS UNTIL 1ST WEEK IN MAY    
Prairie Island 2 100   345 KV OFFSITE PWR LINE OOS UNTIL 1ST WEEK IN MAY    
Quad Cities 1 85   COASTDOWN TO REFUELING OUTAGE    
Quad Cities 2 96   100% ELECTRICAL CAPABILITY    

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 0 04/01/2007 REFUELING OUTAGE    
Columbia Generating Station 96   COASTDOWN TO REFUELING OUTAGE *  
Comanche Peak 1 0 02/24/2007 CORE RELOAD COMPLETED *  
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 100   500 KV GATES-#1 LINE OOS; 230 KV MORREL BAY MESA LINE OOS *  
Diablo Canyon 2 57   CIRCULATING WATER TUNNEL SCRAPING 500 KV GATES-#1 LINE OOS; 230 KV MORREL BAY MESA LINE OOS *  
Fort Calhoun 100        
Grand Gulf 1 0 03/18/2007 REFUELING OUTAGE    
Palo Verde 1 100        
Palo Verde 2 100        
Palo Verde 3 100        
River Bend 1 100   CONDENSER VACUUM RELATED ISSUES    
San Onofre 2 99        
San Onofre 3 100        
South Texas 1 100        
South Texas 2 0 03/25/2007 REFUELING OUTAGE    
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Thursday, March 25, 2021