Power Reactor Status Report for May 16, 2002

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BEAVER VALLEY 1 100        
BEAVER VALLEY 2 100        
CALVERT CLIFFS 1 0 02/15/2002 REFUELING OUTAGE - FUEL RELOAD IN PROGRESS    
CALVERT CLIFFS 2 100        
FITZPATRICK 1 100        
GINNA 1 100        
HOPE CREEK 1 100        
INDIAN POINT 2 100        
INDIAN POINT 3 100        
LIMERICK 1 100        
LIMERICK 2 100        
MILLSTONE 2 100        
MILLSTONE 3 100        
NINE MILE POINT 1 0 05/15/2002 PLANNED MAINTENANCE OUTAGE *  
NINE MILE POINT 2 100        
OYSTER CREEK 1 100        
PEACH BOTTOM 2 100        
PEACH BOTTOM 3 100        
PILGRIM 1 100        
SALEM 1 100        
SALEM 2 1   STARTUP IN PROGRESS - PLANT AT .5% POWER    
SEABROOK 1 0 05/04/2002 REFUELING OUTAGE    
SUSQUEHANNA 1 98     *  
SUSQUEHANNA 2 100        
THREE MILE ISLAND 1 100        
VERMONT YANKEE 1 0 05/11/2002 MID-CYCLE MAINTENANCE OUTAGE TO REPLACE FAILED FUEL - REACTOR VESSEL HEAD REMOVED    

Region 2

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BROWNS FERRY 1 0 03/03/1985 DEFUELED    
BROWNS FERRY 2 100        
BROWNS FERRY 3 100        
BRUNSWICK 1 100        
BRUNSWICK 2 100        
CATAWBA 1 0 04/26/2002 REFUELING OUTAGE *  
CATAWBA 2 100        
CRYSTAL RIVER 3 100        
FARLEY 1 100        
FARLEY 2 100        
HARRIS 1 100        
HATCH 1 100        
HATCH 2 98     *  
MCGUIRE 1 100        
MCGUIRE 2 100        
NORTH ANNA 1 100        
NORTH ANNA 2 100        
OCONEE 1 100        
OCONEE 2 100        
OCONEE 3 100        
ROBINSON 2 100        
SAINT LUCIE 1 100        
SAINT LUCIE 2 100        
SEQUOYAH 1 100        
SEQUOYAH 2 0 04/14/2002 REFUELING OUTAGE    
SUMMER 1 0 04/19/2002 REFUELING OUTAGE - FUEL RELOAD IN PROGRESS    
SURRY 1 100        
SURRY 2 100        
TURKEY POINT 3 100        
TURKEY POINT 4 100        
VOGTLE 1 100        
VOGTLE 2 100        
WATTS BAR 1 100        

Region 3

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BRAIDWOOD 1 100        
BRAIDWOOD 2 100     *  
BYRON 1 100        
BYRON 2 100   MEASURED STEAM GENERATOR TUBE LEAKAGE = 35 GPD *  
CLINTON 1 73   INCREASING POWER *  
COOK 1 0 05/04/2002 REFUELING OUTAGE - DEFUELED    
COOK 2 30   CHEMISTRY HOLD *  
DAVIS BESSE 1 0 02/15/2002 REFUELING OUTAGE - FUEL SHUFFLE COMPLETE    
DRESDEN 2 97   100% ELECTRICAL CAPABILITY    
DRESDEN 3 100        
DUANE ARNOLD 1 94   100% ELECTRICAL CAPABILITY    
FERMI 2 100        
KEWAUNEE 1 28   CHEMISTRY HOLD *  
LASALLE 1 100        
LASALLE 2 100        
MONTICELLO 1 100        
PALISADES 1 100        
PERRY 1 100        
POINT BEACH 1 100        
POINT BEACH 2 71   INCREASING POWER *  
PRAIRIE ISLAND 1 100        
PRAIRIE ISLAND 2 100        
QUAD CITIES 1 100        
QUAD CITIES 2 96   100% ELECTRICAL POWER    

Region 4

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
ARKANSAS NUCLEAR 1 100        
ARKANSAS NUCLEAR 2 100     *  
CALLAWAY 1 100        
COLUMBIA GENERATING 100        
COMANCHE PEAK 1 100        
COMANCHE PEAK 2 100        
COOPER 1 0 05/14/2002 SHUT DOWN FOR EHC MAINTENANCE *  
DIABLO CANYON 1 0 04/28/2002 REFUELING OUTAGE - REFUELED    
DIABLO CANYON 2 100        
FT CALHOUN 1 0 05/03/2002 REFUELING OUTAGE - DEFUELED *  
GRAND GULF 1 100        
PALO VERDE 1 99        
PALO VERDE 2 97        
PALO VERDE 3 99        
RIVER BEND 1 4   HEATING UP *  
SAN ONOFRE 2 98   COASTDOWN TO REFUELING OUTAGE *  
SAN ONOFRE 3 100        
SOUTH TEXAS 1 98        
SOUTH TEXAS 2 100        
WATERFORD 3 100        
WOLF CREEK 1 0 05/13/2002 MAINTENANCE OUTAGE    

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours