Power Reactor Status Report for May 5, 2002

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BEAVER VALLEY 1 100        
BEAVER VALLEY 2 100        
CALVERT CLIFFS 1 0 02/15/2002 REFUELING OUTAGE - DEFUELED    
CALVERT CLIFFS 2 100        
FITZPATRICK 1 100        
GINNA 1 100        
HOPE CREEK 1 100        
INDIAN POINT 2 100        
INDIAN POINT 3 100        
LIMERICK 1 100        
LIMERICK 2 100        
MILLSTONE 2 100        
MILLSTONE 3 100        
NINE MILE POINT 1 100        
NINE MILE POINT 2 100        
OYSTER CREEK 1 100        
PEACH BOTTOM 2 100        
PEACH BOTTOM 3 100        
PILGRIM 1 100        
SALEM 1 100        
SALEM 2 0 04/04/2002 REFUELING OUTAGE    
SEABROOK 1 0 05/04/2002 REFUELING OUTAGE *  
SUSQUEHANNA 1 99     *  
SUSQUEHANNA 2 100        
THREE MILE ISLAND 1 100        
VERMONT YANKEE 1 91   POWER LIMITED DUE TO FIVE POTENTIAL FUEL FAILURES    

Region 2

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BROWNS FERRY 1 0 03/03/1985 DEFUELED    
BROWNS FERRY 2 85   INCREASING POWER *  
BROWNS FERRY 3 100        
BRUNSWICK 1 100        
BRUNSWICK 2 100        
CATAWBA 1 0 04/26/2002 REFUELING OUTAGE - DEFUELED    
CATAWBA 2 100        
CRYSTAL RIVER 3 100        
FARLEY 1 12   PLANT RECOVERY FROM REACTOR SCRAM, SEE EN #38885) *  
FARLEY 2 100        
HARRIS 1 100        
HATCH 1 100        
HATCH 2 100        
MCGUIRE 1 100        
MCGUIRE 2 100        
NORTH ANNA 1 100        
NORTH ANNA 2 100        
OCONEE 1 100        
OCONEE 2 100        
OCONEE 3 100        
ROBINSON 2 100        
SAINT LUCIE 1 100        
SAINT LUCIE 2 100        
SEQUOYAH 1 100        
SEQUOYAH 2 0 04/14/2002 REFUELING OUTAGE - DEFUELED    
SUMMER 1 0 04/19/2002 REFUELING OUTAGE - DEFUELED    
SURRY 1 65   HOLDING POWER AT THIS LEVEL TO PERFORM ISOLATED PHASE BUS DUCT FAN MAINTENANCE    
SURRY 2 100        
TURKEY POINT 3 100        
TURKEY POINT 4 100        
VOGTLE 1 100        
VOGTLE 2 100        
WATTS BAR 1 0 05/03/2002 MAINTENANCE OUTAGE *  

Region 3

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
BRAIDWOOD 1 100        
BRAIDWOOD 2 0 04/19/2002 REFUELING OUTAGE    
BYRON 1 100        
BYRON 2 100   MEASURED STEAM GENERATOR TUBE LEAKAGE = 29 GPD *  
CLINTON 1 1   PLANT STARTUP IN PROGRESS *  
COOK 1 0 05/04/2002 REFUELING OUTAGE *  
COOK 2 100        
DAVIS BESSE 1 0 02/15/2002 REFUELING OUTAGE - FUEL SHUFFLE COMPLETE    
DRESDEN 2 62   REDUCED POWER FOR MAINTENANCE AND TESTING *  
DRESDEN 3 100        
DUANE ARNOLD 1 94   100% ELECTRICAL CAPABILITY    
FERMI 2 100        
KEWAUNEE 1 100     *  
LASALLE 1 100        
LASALLE 2 100        
MONTICELLO 1 100        
PALISADES 1 100        
PERRY 1 100        
POINT BEACH 1 100     *  
POINT BEACH 2 0 04/12/2002 REFUELING OUTAGE    
PRAIRIE ISLAND 1 100        
PRAIRIE ISLAND 2 100        
QUAD CITIES 1 100        
QUAD CITIES 2 100     *  

Region 4

Unit Power Down Reason or Comment Change in report(*) Number of Scrams(#)
ARKANSAS NUCLEAR 1 100        
ARKANSAS NUCLEAR 2 17   PLANT STARTUP IN PROGRESS - READY TO SYNCH TO GRID *  
CALLAWAY 1 70   HOLDING POWER AT THIS LEVEL TO PERFORM SCHEDULED MAIN FEEDWATER PUMP MAINTENANCE    
COLUMBIA GENERATING 100        
COMANCHE PEAK 1 100        
COMANCHE PEAK 2 28   HOLDING POWER FOR XENON *  
COOPER 1 100        
DIABLO CANYON 1 0 04/28/2002 REFUELING OUTAGE - OFFLOADING FUEL *  
DIABLO CANYON 2 100        
FT CALHOUN 1 0 05/03/2002 REFUELING OUTAGE *  
GRAND GULF 1 100        
PALO VERDE 1 99        
PALO VERDE 2 97        
PALO VERDE 3 99        
RIVER BEND 1 100        
SAN ONOFRE 2 100        
SAN ONOFRE 3 100        
SOUTH TEXAS 1 100        
SOUTH TEXAS 2 100        
WATERFORD 3 100        
WOLF CREEK 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Wednesday, March 24, 2021