Public Meetings for 2003
This page lists, in chronological order, the notices, slides and summaries documenting the public meetings held concerning Reactor Vessel Head Degradation for 2003. To learn about future meetings, see our public meeting schedule page.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
| Date |
Description |
|---|---|
| 12/29/03
|
Category 1 Meeting: Discussion by the licensee
of its activities associated with the assessment and actions being
taken to address operational performance, safety culture, and safety
conscious work environment issues. Contact: Jan Strasma, 630-829-9663 |
| 12/19/03 | Category 1 meeting: Discuss the results
of the Restart Assessment Team Inspection. Discuss the results of
Management and Human Performance Team Inspection. Contact: Jan Strasma, 630-829-9663 or Christine Lipa, 630-829-9619 |
| 12/10/03 | Category 1 meeting: Discuss the licensee's
improvement plans relating to corrective action program implementation
weaknesses identified during the Corrective Action Team Inspection.
Focus will be in the area of engineering activities before and after
plant restart. Contact: Julio Lara, 630-829-9731 |
| 12/03/03 | Category 3 Meeting: Present to the
local public the status of the NRC's Oversight Panel activities
fo rthe Davis-Besse Nuclear Power Station |
| 12/03/03 | Category 1 Meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process |
| 11/12/03 RESCHEDULED FROM 11/04/03 |
Category 3 Meeting: Present to the local
public the status of the NRC's Oversight Panel activities for the
Davis-Besse Nuclear Power Station Contact: Christine Lipa, 630-829-9619 |
| 11/12/03 RESCHEDULED FROM 11/04/03 |
Category 1 Meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process. |
| 10/30/03 | Category 2 Meeting: Corrosion of Reactor
Pressure Boundary Materials in Boric Acid Solutions
Contact: William Cullen 301-415-7510 |
| 10/21/03 | Category 1 Meeting: Discuss the modification
of the Davis-Besse high pressure injection pumps. Contact: Jon Hopkins, 301-415-3027
|
| 10/08/03 | Category 1 Meeting: Discuss the results of the Corrective Action Team Inspection and System Health Inspection Contact: Christine Lipa, 630-829-9619 |
| 10/07/03 | Category 3 Meeting: Present to the local public the status of the NRC's Oversight Panel activities for the Davis-Besse Nuclear Power Station Contact: Christine Lipa, 630-829-9619 |
| 10/07/03 | Category 1 Meeting: Discuss licensee performance and progress on the Return to Service Plan as part of the IMC 0350 Process. Contact: Christine Lipa, 630-829-9619 |
| 09/29/03 - 10/02/03 |
Nickel-Base Alloy, Vessel Penetration
Conference |
| 10/01/03 | Safety Culture Public Meeting Contact: Christine Lipa, 630-829-9619 |
| 09/17/03 | Category 3 Meeting: Re: 10 CFR 2.206
Petition on Davis-Besse. Allow petitioners to provide any relevant
additional explanation and support for petition request. |
| 09/10/03 | Category 3 Meeting: Present to the
local public the status of the NRC's Oversight Panel activities
for the Davis-Besse Nuclear Power Station |
| 09/10/03 | Category 1 Meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process. |
| 08/12/03 | Category 1 Meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process |
| 08/12/03 | Category 3 Meeting: Present to the local
public the status of the NRC's Oversight Panel activities fo rthe
Davis-Besse Nuclear Power Station |
| 07/09/03 | Category 3 Meeting: Present to the local
public the status of the NRC's Oversight Panel activities for the
Davis-Besse Nuclear Power Station |
| 07/09/03 | Category 1 Meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process |
| 06/19/03 | Category 1 Meeting: Discuss the Plans
for Modifying the Davis-Besse High Pressure Injection Pumps |
| 06/04/03 | Category 2 Meeting: Discussion of actions
to address Davis-Besse Lessons Learned Task Force Recommendations |
| 06/03/03 | Category 1 Meeting: Discuss licensee performance
and progress on the Return to Service Plan as part of the IMC 0350
Process Contact: Christine Lipa, 630-829-9619 |
| 06/03/03 | Category 3 Meeting: Present to the local
public the status of the NRC's Oversight Panel activities for the
Davis-Besse Nuclear Power Station Contact: Christine Lipa, 630-829-9619 |
| 05/07/03 | Category 1 Meeting: Discuss the licensee's
plans to address Engineering Design Issue Resolution |
| 05/06/03 | Category 1 Meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process |
| 05/06/03 | Category 3 Meeting: Present to the local
public the status of the NRC's Oversight Panel activities for the
Davis-Besse Nuclear Power Station
Location: Camp Perry Clubhouse, Port Clinton, OH |
| 04/15/03 | Category 1 Meeting: Discuss preliminary
findings and observations from an NRC supplemental inspection conducted
to review the licensee's evaluation of two "White" radiological
performance issues and other aspects of the radiation protection
program restart readiness. |
| 04/15/03 | Category 1 Meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process
|
| 04/15/03 | Category 3 Meeting: Present to the local
public the status of the NRC's Oversight Panel activities for the
Davis-Besse Nuclear Power Station |
| 04/04/03 | Category 1 Meeting: Discuss the Results
of the Davis-Besse Reactor Vessel Incore Monitoring Instrumentation
Nozzles Reactor Coolant Leakage Simulation |
| 03/24/03 - 03/26/03 Rescheduled for 9/29/03-10/02/03 |
Nickel-Base Alloy, Vessel
Penetration Conference |
| 03/11/03 | Category 1 Meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process |
| 03/11/03 | Category 3 Meeting: Present to the
local public the status of the NRC's Oversight Panel activities
for the Davis-Besse Nuclear Power Station |
| 02/24/03 | Category 2 Meeting: To discuss with Industry
the Orders Issued on Reactor Vessel Head Inspections. Contact: Steven Bloom, 301-415-1313 |
| 02/11/03 | Category 1 Meeting: Discuss licensee performance
and progress on the Return to Service Plan as part of the IMC 0350
Process Contact: Christine Lipa, 630-829-9619
|
| 02/11/03 | Category 3 Meeting: Present to the local
public the status of the NRC's Oversight Panel activities for the
Davis-Besse Nuclear Power Station Contact: Christine Lipa, 630-829-9619 |
| 01/30/03 | Category 1 Meeting: Discuss the licensee's
plans to address Safety Conscious Work Environment Contact: Christine Lipa, 630-829-9619 |
| 01/14/03 | Category 1 meeting: Discuss licensee
performance and progress on the Return to Service Plan as part of
the IMC 0350 Process
|
| 01/14/03 | Category 3 meeting: Present to the
local public the status of the NRC's Oversight Panel activities
for the Davis-Besse Nuclear Power Station
|
For related information see Generic Activities on Alloy 600 Cracking.