Plant-Specific Actions in Response to the Japan Nuclear Accident: Vermont Yankee Nuclear Power Station

Vermont Yankee is no longer an operating reactor. Please see Vermont Yankee decommissioning information.

Orders and Requests for Information Licensee Responses/Submittals


Order for Mitigation Strategies to Respond to Extreme Natural Events Resulting in the Loss of Power at Plants  [+] Show More
Modified Order for Ensuring Reliable Hardened Containment Vents  [+] Show More
  • Licensee Request to Rescind Order
  • NRC Order Rescission
  • Licensee Phase 1 Integrated Plan (due June 30, 2014)
  • NRC Safety Evaluation of Phase 1 Integrated Plan
  • Licensee Phase 2 Integrated Plan (due December 31, 2015)
  • NRC Safety Evaluation of Phase 2 Integrated Plan
  • NRC Inspection Report
  • Status Updates
    • 1st update (due December 31, 2014)
    • 2nd update (due June 30, 2015)
    • 3rd update (due December 31, 2015)
    • 4th update (due June 30, 2016)
Order for Enhancing Spent Fuel Pool Instrumentation  [+] Show More

Request for Information

Request for Information for Seismic and Flooding Reevaluations and Walkdowns, and Reevaluations of Emergency Communications Systems and Staffing Levels
[+] Show More

Page Last Reviewed/Updated Monday, November 02, 2015