Sequoyah Nuclear Plant, Units 1 and 2 - License Renewal Application

Photo of Sequoyah Nuclear Plant, Units 1 and 2

On this page:

Application Information

To top of page

License Renewal Review Schedule*

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

To top of page

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 01/15/13  01/15/13
Publish Federal Register Notice (FRN) – LRA availability 02/2013  02/22/13
Publish FRN – acceptance/rejection and opportunity for hearing 03/2013  03/05/13
Publish FRN – environmental scoping meeting 03/2013 03/08/13 
Audit – Scoping & Screening Methodology 03/11/13 03/11/13 
Audit – Aging Management Programs 03/18/13 03/18/13
Public Meeting – License Renewal Overview and Environmental Scoping meeting 04/03/13 04/03/13
Audit – Environmental 04/08/13 04/08/13
Deadline for filing hearing requests and petitions for intervention 05/06/13 05/06/13
Environmental scoping period ends 05/03/13 05/03/13
Inspection – Regional 11/18/13 & 12/08/13 11/18 & 12/08/13
Issue draft supplemental environmental impact statement (SEIS) 07/2014  
U.S. Environmental Protection Agency FRN published – draft SEIS available for comments 08/2014  
Public Meeting – draft SEIS meeting 08/2014  
Issue safety evaluation report (SER) with open items 01/2015  
End of draft SEIS comment period 09/2014  
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting TBD  
Issue final SEIS 03/2015  
U.S. Environmental Protection Agency FRN published – availability of final SEIS 04/2015  
Issue final SER 05/2015  
ACRS full committee meeting TBD  
D Decision – Director, NRR 06/2015  
Commission decision, if hearing granted TBD  

Note: The Sequoyah Nuclear Plant review schedule was revised as described in the letter below:

To top of page

Project Managers for Sequoyah Nuclear Plant

Sequoyah Nuclear Plant PMs
License Renewal (Safety) Rick Plasse
License Renewal (Environmental) David Drucker
Lead Power Plant Siva Lingam

To top of page

Page Last Reviewed/Updated Tuesday, April 08, 2014