| Milestones | Schedule Date | Actual Date |
|---|---|---|
| Receive License Renewal (LR) Application | 03/24/05 | 03/24/05 |
| Federal Register Notice (FRN) published - Receipt & Availability Review | 04/06/05 | 04/06/05 |
| Public Information Meeting - LR Process & Safety Review Overview | 04/20/05 | 04/20/05 |
| FRN published - Acceptability/Opportunity for Hearing | 05/10/05 | 05/12/05 |
| FRN published - Intent/Environmental Scoping Meeting | 06/03/05 | 06/02/05 |
| Public Exit Meeting - Scoping & Screening Methodology Audit | 06/24/05 | 06/24/05 |
| Public Meeting - Environmental Scoping | 06/30/05 | 06/30/05 |
| Deadline for filing hearing requests and petitions for intervention | 07/11/05 | 07/11/05 |
| Environmental Scoping Periods Ends | 08/02/05 | 08/02/05 |
| Public Exit Meeting - AMP/AMR Audit | 08/18/05 | 08/18/05 |
| Environmental Requests for Additional information(RAIs) - issued | 08/26/05 | 08/26/05 |
| Environmental RAIs - responses received | 10/07/05 | 10/07/05 |
| Safety RAIs - issued | 11/01/05 | 11/07/05 |
| Safety RAI - responses received | 12/01/05 | 12/07/05 |
| Public Exit Meeting - Scoping & Screening/AMP Inspections | 02/22/06 | 02/22/06 |
| Draft Supplemental Environmental Impact Statement (SEIS) Issued | 02/10/06 | 01/23/06 |
| FRN Published - Availability/Comment on draft SEIS | 02/17/06 | 02/02/06 |
| Public Meeting - draft SEIS | 03/22/06 | 03/22/06 |
| End of draft SEIS comment period | 05/04/06 | 05/04/06 |
| Safety Evaluation Report (SER) with Open Item(s) - Issued | 05/01/06 | 04/26/06 |
| ACRS Subcommittee Meeting on SER with Open Item(s) | 05/30/06 | 05/30/06 |
| SER Open Item(s) - Response(s) Received | 06/23/06 | N/A |
| Final SEIS - issued | 09/22/06 | 09/19/06 |
| FRN published - Availability of Final SEIS | 09/29/06 | 09/27/06 |
| SER - issued | 08/02/06 | 07/28/06 |
| ACRS Full Committee Meeting on SER | 09/07/06 | 09/07/06 |
| Decision - Director, NRR (license issued, if approved and no hearing is granted - 22 months) | 11/08/06 | 11/08/06 |
NUREG-1437,"Generic Environmental Impact Statement for License Renewal of Nuclear Plants, " Supplement 26, Regarding Monticello Nuclear Generating Plant, was published September 2006.
This supplement documents the NRC staff's review of the environmental issues at Monticello regarding Nuclear Management Company's (NMC) application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's recommendation regarding the proposed actions.
The following links on this page are to documents in our Agencywide Documents Access and Management System (ADAMS). ADAMS documents are provided in either Adobe Portable Document Format (PDF) or Tagged Image File Format (TIFF). To obtain free viewers for displaying these formats, see our Plugins, Viewers, and Other Tools. If you have problems with viewing or printing documents from ADAMS, please contact the Public Document Room staff.
The NRC staff reviewed the Monticello license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was issued April 26, 2006, as "Safety Evaluation Report Related to the License Renewal of the Monticello Nuclear Generating Plant." The report is available in ADAMS under accession number ML061170030.
In October 2006, the report "Safety Evaluation Report Related to the License Renewal of the Monticello Generating Plant" was issued as NUREG-1865. The report is available in ADAMS under accession number ML063050414.
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
| Monticello Nuclear Generating Plant PMs | |
|---|---|
| License Renewal | Daniel Merzke |
| Lead Power Plant | Peter Tam |
| Environmental | Jennifer Davis |
|