Davis-Besse Nuclear Power Station, Unit 1 – License Renewal Application

On this page:
- Application Information
- License Renewal Review Schedule
- Project Managers for Davis-Besse Nuclear Power Station, Unit 1
Application Information:
License Renewal Review Schedule*:
* These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
| Milestones | Schedule Date | Actual Date |
|---|---|---|
| Receive license renewal application (LRA) | 08/30/10 | 08/30/10 |
| Publish Federal Register Notice (FRN) - LRA receipt and availability | 09/17/10 | 09/20/10 |
| Publish FRN - LRA acceptability and opportunity for hearing | 10/20/10 | 10/25/10 |
| Publish FRN – intent to conduct environmental scoping | 10/20/10 | 10/28/10 |
| Public Meeting - license renewal process and environmental scoping | 11/04/10 | 11/04/10 |
| Deadline for filing hearing requests and petitions for intervention | 12/24/10 | 12/24/10 |
| Environmental scoping periods ends | 12/27/10 | 12/27/10 |
| Audit - scoping and screening methodology | 01/24/11 | 01/24/11 |
| Audit - aging management programs (AMPs) | 02/14/11 | 02/14/11 |
| Audit - environmental | 03/07/11 | 03/07/11 |
| Inspection - scoping, screening, and AMPs | 04/2011 | 04/25/11 |
| Environmental Requests for Additional Information (RAIs) - Issued | 04/08/11 | 02/23/11 |
| Safety RAIs - Issued | 04/29/11 | 04/29/11 |
| Environmental RAIs - Response Received | 05/13/11 | 03/23/11 |
| Safety RAI - Responses Received | 05/30/11 | 05/30/11 |
| Issue draft supplemental environmental impact statement (SEIS) | TBD | |
| Issue safety evaluation report (SER) with open item(s) | 7/2012 | |
| Public Meeting - draft SEIS | TBD | |
| ACRS subcommittee meeting on SER with open item(s) | 09/19/12 | |
| End of comment period for the draft SEIS | TBD | |
| Issue final SEIS | TBD | |
| Issue SER | 10/2012 | |
| ACRS full committee meeting on SER | 12/2012 | |
| Decision – Director, Office of Nuclear Reactor Regulation | TBD | |
| Commission decision (hearing pending) | TBD |
Note: The Davis-Besse review schedule was revised as described in the letter below:
- Revised Schedule Letter (March 9, 2012)
- Revised Schedule Letter (January 31, 2012)
- Revised Schedule Letter (December 27, 2011)
- Revised Schedule Letter (October 31, 2011)
Project Managers for Davis-Besse
| Davis-Besse Nuclear Power Station, Unit 1 PMs | |
|---|---|
| License Renewal (Safety) | Samuel Cuadrado de Jesús |
| License Renewal (Environmental) | Paula Cooper |
| Lead Power Plant | Michael Mahoney |