Callaway Plant, Unit 1 – License Renewal Application

On this page:
- Application Information
- License Renewal Review Schedule
- Safety Evaluation Report
- Project Managers for Callaway Plant, Unit 1
Application Information:
- License Renewal Application
- Applicant's Environmental Report
- Cover through Chapter 2 – 16.1 MB
- Chapter 3 through Attachment D – 21.5 MB
- Attachment E through End – 7.0 MB
- Full Environmental Report – 43.7 MB
- Full Environmental Report, reduced file size – 10.8 MB
License Renewal Review Schedule*:
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
| Milestones | Schedule Date | Actual Date |
|---|---|---|
| Receive license renewal application (LRA) | 12/19/11 | 12/19/11 |
| Publish Federal Register Notice (FRN) – LRA availability | 01/2012 | 01/03/12 |
| Publish FRN – acceptance/rejection and opportunity for hearing | 02/2012 | 02/24/12 |
| Publish FRN – environmental scoping meeting | 02/2012 | 02/24/12 |
| Public Meeting – License Renewal Overview and Environmental Scoping meeting | 03/14/12 | 03/14/12 |
| Deadline for filing hearing requests and petitions for intervention | 04/24/12 | 04/24/12 |
| Environmental scoping period ends | 04/24/12 | 04/24/12 |
| Audit – Scoping & Screening Audit Methodology | 04/16/12 | 04/16/12 |
| Audit – Aging Management Programs | 04/30/12 | 04/30/12 |
| Audit – Environmental | 05/22/12 | 05/22/12 |
| Issue safety evaluation report (SER) with open items | 04/2013 | 04/23/13 |
| Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting | TBD | |
| Issue draft supplemental environmental impact statement (SEIS) | 08/2013 | |
| Publish FRN – draft SEIS available for comments | 08/2013 | |
| Public Meeting – draft SEIS meeting | 09/2013 | |
| End of draft SEIS comment period | 09/2013 | |
| Issue final SER | 09/2013 | |
| ACRS full committee meeting | 10/2013 | |
| Issue final SEIS | 04/2014 | |
| U.S. Environmental Protection Agency FRN Published – availability of final SEIS | 04/2014 | |
| Decision – Director, Office of Nuclear Reactor Regulation (22 months if no hearing) | TBD | |
| Commission decision (30 months if hearing) | TBD |
Safety Evaluation Report
The NRC staff reviewed the Callaway Plant, Unit 1, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was issued on April 23, 2013, as "Safety Evaluation Report with Open Items Related to the License Renewal of Callaway Plant, Unit 1."
Project Managers for Callaway Plant
| Callaway Plant, Unit 1 PMs | |
|---|---|
| License Renewal (Safety) | Samuel Cuadrado de Jesús |
| License Renewal (Environmental) | Carmen Fells |
| Lead Power Plant | Fred Lyon |