License Renewal Review Schedule*:

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 12/19/11 12/19/11
Publish Federal Register Notice (FRN) – LRA availability 01/2012 01/03/12
Publish FRN – acceptance/rejection and opportunity for hearing 02/2012 02/24/12
Publish FRN – environmental scoping meeting 02/2012 02/24/12
Public Meeting – License Renewal Overview and Environmental Scoping meeting 03/14/12 03/14/12 
Deadline for filing hearing requests and petitions for intervention 04/24/12 04/24/12
Environmental scoping period ends 04/24/12  04/24/12
Audit – Scoping & Screening Audit Methodology 04/16/12 04/16/12
Audit – Aging Management Programs 04/30/12 04/30/12
Audit – Environmental 05/22/12 05/22/12
Issue safety evaluation report (SER) with open items 04/2013 04/23/13
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting TBD  
Issue draft supplemental environmental impact statement (SEIS) 08/2013  
Publish FRN – draft SEIS available for comments 08/2013  
Public Meeting – draft SEIS meeting 09/2013  
End of draft SEIS comment period 09/2013  
Issue final SER 09/2013  
ACRS full committee meeting 10/2013  
Issue final SEIS 04/2014  
U.S. Environmental Protection Agency FRN Published – availability of final SEIS 04/2014  
Decision – Director, Office of Nuclear Reactor Regulation (22 months if no hearing) TBD  
Commission decision (30 months if hearing) TBD  

To top of page

Safety Evaluation Report

The NRC staff reviewed the Callaway Plant, Unit 1, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was issued on April 23, 2013, as "Safety Evaluation Report with Open Items Related to the License Renewal of Callaway Plant, Unit 1."

To top of page

Project Managers for Callaway Plant

Callaway Plant, Unit 1 PMs
License Renewal (Safety) Samuel Cuadrado de Jesús
License Renewal (Environmental) Carmen Fells
Lead Power Plant Fred Lyon

To top of page