Byron and Braidwood Nuclear Stations, Units 1 and 2: License Renewal Application

Byron Facility Braidwood Facility
Photograph of Byron Nuclear Station Photograph of Braidwood Nuclear Station

On this page:

Application Information:

(To top of page)

License Renewal Review Schedule*

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 05/29/13 05/29/13
Publish Federal Register Notice (FRN) – LRA availability 06/2013 06/13/13
Publish FRN – acceptance/rejection and opportunity for hearing 07/2013 07/24/13
Publish FRN – environmental scoping meeting 07/2013 08/06/13
Audit – Scoping & Screening Methodology 1 (at Byron) 07/2013 07/20/13
Audit – Aging Management Programs 1 (at Byron) 08/2013 08/20/13
Public Meeting - License Renewal Overview and Environmental Scoping meetings 08/20/13-08/21/13 08/20/13
(Byron)
08/21/13
(Braidwood)
Deadline for filing hearing requests and petitions for intervention 09/2013 09/23/13
Audit – Environmental (Byron) 09/2013 09/19/13
Environmental scoping period ends* 09/2013 09/27/13
Audit – Scoping & Screening Methodology 2 (at Braidwood) 10/2013 12/02/13-12/04/13
Audit – Aging Management Programs 2 (at Braidwood) 10/2013 12/02/13-12/06/13
Audit – Environmental (Braidwood) 11/2013 11/19/13
Regional Inspection (Byron) 08/2014 08/04/14-08/08/14
and 08/22/14
Regional Inspection (Braidwood) 09/2014 09/15/14-09/26/14
Issue safety evaluation report (SER) with open items 11/2014 10/30/14
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 12/2014 12/03/14
Issue draft supplemental environmental impact statement (SEIS) - Byron 12/2014 12/31/14
Publish FRN – Byron draft SEIS available for comments 01/2015 01/02/15
Public Meeting – Byron draft SEIS meeting 02/2015 02/03/15
End of draft SEIS comment period – Byron 02/2015 02/20/15
Issue draft SEIS - Braidwood 03/2015 03/18/15
Publish FRN – Braidwood draft SEIS available for comments 03/2015 03/25/15
Public Meeting – Braidwood draft SEIS meeting 04/2015 04/21/15
End of draft SEIS comment period – Braidwood 05/2015 05/12/15
Issue final SER 07/2015  
Issue final SEIS – Byron 07/2015  
U.S. Environmental Protection Agency FRN Published – availability of final SEIS – Byron 08/2015  
ACRS full committee meeting 09/2015  
Issue final SEIS – Braidwood 09/2015  
U.S. Environmental Protection Agency FRN Published – availability of final SEIS – Braidwood 09/2015  
Decision – Director, NRR 11/2015  
Commission decision, if hearing granted TBD  

The NRC has documented the results of the environmental scoping period in the Byron Scoping Summary Report and Braidwood Scoping Summary Report.

Note: The Byron and Braidwood Nuclear Stations, Units 1 and 2, review schedule was revised as described in the letter below:

(To top of page)

Safety Evaluation Report

The NRC staff reviewed the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on October 30, 2014, as "Safety Evaluation Report with Open Items Related to the License Renewal of Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2."

(To top of page)

Environmental Impact Statements

NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Byron Station, Units 1 and 2 (NUREG-1437, Supplement 54) Draft Report for Comment," was published in December 2014. This supplement documents the NRC staff's review of the environmental issues at Byron Station, Units 1 and 2 regarding the Exelon Generation Company, LLC application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff's preliminary recommendation regarding the proposed action.

NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Braidwood Station, Units 1 and 2, (NUREG-1437, Supplement 55) Draft Report for Comment," was published in March 2015. This supplement documents the NRC staff's review of the environmental issues at Braidwood Station, Units 1 and 2, regarding the Exelon Generation Company, LLC application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal) and the environmental impacts of alternatives to the proposed action. It also includes the NRC staff's preliminary recommendation regarding the proposed action.

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
04/21/2015

Meeting to discuss draft environmental impact statement for Braidwood Nuclear Station.

02/03/2015

Meeting to discuss draft environmental impact statement for Byron Nuclear Station.

08/21/2013

Meeting to discuss the license renewal process and environmental scoping for Braidwood Nuclear Station.

08/20/2013

Meeting to discuss the license renewal process and environmental scoping for Byron Nuclear Station.

(To top of page)

Project Managers for Byron-Braidwood Nuclear Stations

Byron-Braidwood Plant PMs
License Renewal (Safety) John Daily
License Renewal (Environmental-Byron) Lois James
License Renewal (Environmental-Braidwood) Tam Tran
Lead Power Plant Joel Wiebe