Plant Applications for License Renewal

Future Submittals of Applications:

Fiscal YearLicense Renewal Application (LRA)ApplicantLetter of Intent
(ADAMS Accession No.)
Submission Date
2027Watts Bar Nuclear Plant, Unit 1Tennessee Valley AuthorityML24085A212Oct. to Dec. 2026

 

 

 

Applications Received and Under Acceptance Review:

Plant Name and Unit(s)Application Received
Currently No Applications Received and Under Acceptance Review

 

 

 

Applications Currently Under Review:

Plant Name and Unit(s)Application Received
Currently No Applications Under Review

 

 

 

Completed Applications:

(Includes application, review schedule, supplemental environmental impact statement, and safety evaluation report.)

Plant Name and Unit(s)Application ReceivedRenewed License IssuedDate Entering Extended Operation
Calvert Cliffs 1 & 204/10/9803/23/0007/31/14 (Unit 1)
08/13/16 (Unit 2)
Oconee 1, 2 & 307/07/9805/23/0002/06/13 (Unit 1)
10/06/13 (Unit 2)
07/19/14 (Unit 3)
Arkansas Nuclear One 102/01/0006/20/0105/20/14
Turkey Point 3 & 409/11/0006/06/0207/19/12 (Unit 3)
04/10/13 (Unit 4)
Edwin I. Hatch 1 & 203/01/0006/15/0208/06/14 (Unit 1)
06/13/18 (Unit 2)
North Anna 1 & 205/29/0103/20/0304/01/18 (Unit 1)
08/21/20 (Unit 2)
Surry 1 & 205/29/0103/20/0305/25/12 (Unit 1)
01/29/13 (Unit 2)
Peach Bottom 2 & 307/02/0105/07/0308/08/13 (Unit 2)
07/02/14 (Unit 3)
St. Lucie 1 & 211/30/0110/02/0303/01/16 (Unit 1)
04/06/23 (Unit 2)
Fort Calhoun*01/11/0211/04/0308/09/13
McGuire 1 & 206/14/0112/05/0306/12/21 (Unit 1)
03/03/23 (Unit 2)
Catawba 1 & 206/14/0112/05/0312/05/23 (Unit 1)
12/05/23 (Unit 2)
H.B. Robinson 206/17/0204/19/0407/31/10
V.C. Summer08/06/0204/23/0408/06/22
R.E. Ginna08/01/0205/19/0409/18/09
Dresden 2 & 301/03/0310/28/0412/22/09 (Unit 2)
01/12/11 (Unit 3)
Quad Cities 1 & 203/03/0310/28/0412/14/12 (Unit 1)
12/14/12 (Unit 2)
Joseph M. Farley 1 & 209/15/0305/12/0506/25/17 (Unit 1)
03/31/21 (Unit 2)
Arkansas Nuclear One 210/15/0306/30/0507/17/18
D.C. Cook 1 & 210/31/0308/30/0510/25/14 (Unit 1)
12/23/17 (Unit 2)
Millstone 2 & 301/22/0411/28/0507/31/15 (Unit 2)
11/25/25 (Unit 3)
Point Beach 1 & 202/26/0412/22/0510/05/10 (Unit 1)
03/08/13 (Unit 2)
Browns Ferry 1, 2 & 301/02/0405/04/0612/20/13 (Unit 1)
06/28/14 (Unit 2)
07/02/16 (Unit 3)
Brunswick 1 & 210/18/0406/26/0609/08/16 (Unit 1)
12/27/14 (Unit 2)
Nine Mile Point 1 & 205/27/0410/31/0608/22/09 (Unit 1)
10/31/26 (Unit 2)
Monticello03/24/0511/08/0609/08/10
Palisades03/31/0501/17/0703/24/11
FitzPatrick07/01/0609/08/0810/17/14
Wolf Creek 110/04/0611/20/0803/11/25
Harris 111/16/0612/17/0810/24/26
Oyster Creek******07/22/0504/08/0904/09/09
Vogtle 1 & 206/29/0706/03/0901/16/27 (Unit 1)
02/09/29 (Unit 2)
Three Mile Island 101/08/0810/22/0904/19/14
Beaver Valley 1 & 208/28/0711/05/0901/29/16 (Unit 1)
05/27/27 (Unit 2)
Susquehanna 1 & 209/13/0611/17/0907/17/22 (Unit 1)
03/23/24 (Unit 2)
Cooper09/30/0811/29/1001/18/14
Duane Arnold10/01/0812/16/1002/21/14
Kewaunee08/14/0802/24/11**
Vermont Yankee***01/27/0603/21/1103/21/12
Palo Verde 1, 2 & 312/15/0804/22/1106/01/25 (Unit 1)
04/24/26 (Unit 2)
11/25/27 (Unit 3)
Prairie Island 1 & 204/15/0806/27/1108/09/13 (Unit 1)
10/29/14 (Unit 2)
Salem 1 & 208/18/0906/30/1108/13/16 (Unit 1)
04/18/20 (Unit 2)
Hope Creek 108/18/0907/20/1104/11/26
Columbia Generating Station01/20/1005/22/1212/20/23
Pilgrim 101/27/0605/29/12 +++
Crystal River 312/18/08**** 
Limerick 1 & 206/22/1110/20/1410/26/24 (Unit 1)
06/22/29 (Unit 2)
Callaway 112/19/1103/06/1510/18/24
Sequoyah 1 & 201/15/1309/24/1509/17/20 (Unit 1)
09/15/21 (Unit 2)
Byron 1 & 205/29/1311/19/1510/31/24 (Unit 1)
11/06/26 (Unit 2)
Davis-Besse 108/30/1012/08/1504/22/17
Braidwood 1 & 205/29/1301/27/1610/17/26 (Unit 1)
12/18/27 (Unit 2)
LaSalle 1 & 212/09/1410/19/1604/17/22 (Unit 1)
12/16/23 (Unit 2)
Grand Gulf 111/01/1112/01/1611/02/24
Fermi, Unit 204/30/1412/15/1603/21/25
South Texas Project 1 & 210/28/1009/28/1708/21/27 (Unit 1)
12/16/28 (Unit 2)
Diablo Canyon 1 & 211/24/0904/02/2026*****11/02/44 (Unit 1)
08/26/45 (Unit 2)
Indian Point 2 & 304/30/0709/17/1809/17/18 (Unit 1)
09/17/18 (Unit 2)
River Bend05/31/1712/20/1808/30/25
Waterford 303/23/1612/27/1810/19/24
Seabrook 106/01/1003/12/1903/15/30
Comanche Peak 1 & 210/03/2207/30/2402/08/30 (Unit 1)
02/02/33 (Unit 2)
Perry Nuclear Power Plant, Unit 107/03/2307/07/2511/07/26
Clinton Power Station, Unit 102/14/2412/16/2504/17/27

* Fort Calhoun Station was permanently shut down on October 24, 2016.

** Kewaunee Power Station was permanently shut down on May 7, 2013.

*** Vermont Yankee Nuclear Power Station was permanently shut down on December 29, 2014.

**** The Crystal River Nuclear Generating Plant, Unit 3 application was withdrawn by the licensee on February 6, 2013.  The facility was permanently shut down on February 20, 2013.

***** The previous Diablo Canyon 1 & 2 license renewal application was submitted on November 7, 2018 and withdrawn by the licensee on March 7, 2018. On October 31, 2022, Pacific Gas and Electric sent in a letter to “Request to Resume Review of the Diablo Canyon Power Plant License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application.”  On March 2, 2023, the NRC granted the exemption.

****** Oyster Creek Nuclear Generating Station was permanently shut down on September 7, 2018.

 +++ Pilgrim 1 permanently shut down on May 31, 2019

 

 

 

Industry Activities

Nuclear Energy Institute (NEI) -- Industry representatives also participate in working groups and technical committees, coordinated by the Nuclear Energy Institute, to address generic technical and process issues, and to develop additional guidance related to scoping and aging management programs. The NRC has established a formal feedback process by which the resolution of the generic renewal issues and lessons learned during the review of the initial renewal applications is documented and included in revisions to the implementation guidance. These activities are expected to improve the efficiency and effectiveness of future license renewal reviews.

 

 

 

Subscribe to License Renewal Correspondence for a Specific Plant

To subscribe to all outgoing public correspondence for a specific license renewal application by e-mail, simply go to our Operating Reactors Correspondence page enter your email address, name, select the plant(s) of interest and Subscribe. This correspondence will include all publicly available information for a specific plant.

 

 

 

Page Last Reviewed/Updated Friday, September 11, 2026

Page Last Reviewed/Updated Friday, September 11, 2026