skip navigation links 
 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer BrowseAloud
secondary page banner Return to NRC Home Page
Status of Power Uprate Applications
Approved Applications
Pending Applications
Expected Applications

Pending Applications for Power Uprates

The following power uprates are currently under review by the NRC. The licensees for the following plants have not been authorized by the NRC to operate the plants at power levels that reflect the following increases.

(TYPE -- S = Stretch; E = Extended; MUR= Measurement Uncertainty Recapture)
(TBD = To Be Determined)

NO. PLANT % UPRATE MWt SUBMITTAL DATE PROJECTED COMPLETION
DATE
TYPE
1 Browns Ferry 2 14.3 494 06/25/2004 TBD E
2 Browns Ferry 3 14.3 494 06/25/2004 TBD E
3 Browns Ferry 1 14.3 494 06/28/2004 TBD E
4 Monticello 12.9 229 11/05/2008 TBD E
5 Point Beach 1 17 260 04/07/2009 November 2010 E
6 Point Beach 2 17 260 04/07/2009 November 2010 E
7 Nine Mile Pt. 2 15 521 05/27/2009 July 2010 E
8 Praire Island 1 1.6 27 12/28/2009 July 2010 MUR
9 Praire Island 2 1.6 27 12/28/2009 July 2010 MUR
  Total MWt   2806
     
  Total MWe   935      


Privacy Policy | Site Disclaimer
Wednesday, January 20, 2010