The following power uprates are currently under review by the NRC. The licensees for the following plants have not been authorized by the NRC to operate the plants at power levels that reflect the following increases.
(TYPE -- S = Stretch; E = Extended; MUR= Measurement Uncertainty Recapture)
(TBD = To Be Determined)
| NO. | PLANT | % UPRATE | MWt | SUBMITTAL DATE | PROJECTED COMPLETION DATE |
TYPE |
|---|---|---|---|---|---|---|
| 1 | Browns Ferry 2 | 14.3 | 494 | 06/25/2004 | TBD | E |
| 2 | Browns Ferry 3 | 14.3 | 494 | 06/25/2004 | TBD | E |
| 3 | Browns Ferry 1 | 14.3 | 494 | 06/28/2004 | TBD | E |
| 4 | Monticello | 12.9 | 229 | 11/05/2008 | 3rd Quarter 2013 | E |
| 5 | Braidwood 1 | 1.6 | 58.4 | 06/23/2011 | On Hold[2] | MUR |
| 6 | Braidwood 2 | 1.6 | 58.4 | 06/23/2011 | On Hold[2] | MUR |
| 7 | Byron 1 | 1.6 | 58.4 | 06/23/2011 | On Hold[2] | MUR |
| 8 | Byron 2 | 1.6 | 58.4 | 06/23/2011 | On Hold[2] | MUR |
| 9 | Oconee 1 | 1.6 | 42 | 09/20/2011 | On Hold[1] | MUR |
| 10 | Oconee 2 | 1.6 | 42 | 09/20/2011 | On Hold[1] | MUR |
| 11 | Oconee 3 | 1.6 | 42 | 09/20/2011 | On Hold[1] | MUR |
| 12 | McGuire 1 | 1.7 | 58 | 03/05/2012 | May 2013 | MUR |
| 13 | McGuire 2 | 1.7 | 58 | 03/05/2012 | May 2013 | MUR |
| 14 | Peach Bottom 2 | 12.4 | 437 | 09/28/2012 | June 2014 | E |
| 15 | Peach Bottom 3 | 12.4 | 437 | 09/28/2012 | June 2014 | E |
| 16 | Fermi 2 | 1.6 | 56 | 02/07/2013 | November 2013 | MUR |
| Total MWt | 3116.6 | |||||
| Total MWe | 1038.9 |
[1] NRC letter dated August 31, 2012, to Duke Energy regarding Oconee Power Uprate.
[2] NRC letter dated December 6, 2012, to Exelon Generation Company regarding Braidwood and Byron Uprate.