The following power uprates are currently under review by the NRC. The licensees for the following plants have not been authorized by the NRC to operate the plants at power levels that reflect the following increases.

(TYPE -- MUR= Measurement Uncertainty Recapture, SPU = Stretch Power Uprate, EPU = Extended Power Uprate)

NO. PLANT % UPRATE MWt SUBMITTAL DATE PROJECTED COMPLETION
DATE
TYPE
1 Catawba 1 1.7 58 06/23/2014 Spring 2016 MUR
2 Browns Ferry 1 14.3 494 09/21/2015 Fall 2017 EPU
3 Browns Ferry 2 14.3 494 09/21/2015 Fall 2017 EPU
4 Browns Ferry 3 14.3 494 09/21/2015 Fall 2017 EPU
  Total MWt   1540      
  Total MWe   513      