2008 Public Meetings for Turkey Point, Units 6 and 7 Application

The following table lists, in chronological order, the public meetings that staff of the U.S. Nuclear Regulatory Commission (NRC) conducted with representatives of Florida Power and Light Company (FPL) in 2008, in connection with the review of the combined license (COL) application for Turkey Point, Units 6 and 7. To learn about future meetings, see our Public Meeting Schedule.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
12/05/08 Public Meeting to Discuss Geotechnical and Hydrological Conditions at Turkey Point Site for the Proposed AP1000 Pressurized Water Reactor (PWR) Units 6 and 7
01/16/08 Public Meeting with FPL to Discuss Pre-Application Meteorological Topics Associated with the Turkey Point New Reactor Site