New
Reactors Oversight
A new construction inspection program (CIP) is being developed
for plants licensed in accordance with the requirements of
10 CFR Part 52.
The introduction of "inspections, tests, analyses, and acceptance
criteria" (ITAAC) into the Part 52 licensing process creates a
design specific pre-approved set of performance standards that
the licensee must meet and that the Commission must find have
been met, before the licensee can load fuel and operate the plant.
As a result, a major focus of the CIP is on the licensee work
being performed to support the completion of the ITAAC. However,
additional inspections of quality assurance verification
activities and operational programs will also be needed to
provide assurance that these activities and programs are in
compliance with applicable Nuclear Regulatory Commission (NRC)
requirements. The CIP is being developed to address the specific
needs associated with verifying the successful completion of the
ITAAC as well as to incorporate lessons learned from previous
NRC construction inspections.
Additional background documents of interest for revision of the CIP include
the following:
The following links on this page are to documents in Adobe Portable Document
Format (PDF). See our Plugins, Viewers, and
Other Tools page for more information. For successful viewing of PDF documents on our site please be sure to use the latest version of Adobe.
Inspection Manual Chapters
- IMC 0614, "Documenting 10 CFR 52 Construction Audit Activities"
- IMC 2501, "Early Site Permit (ESP)"
- IMC 2502, "Pre-Combined License (Pre-COL) Phase"
- IMC 2503, "Inspections of Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC)"
- IMC 2504, "Non-ITAAC Inspections"
- IMC 2507, "Vendor Inspections"
- IMC 2508, "Design Certification"

Commission Papers (SECY)
SECY
| Title
| SRM
|
07-0049 |
Construction Inspection Roles And Responsibilities |
|
07-0047 |
Staff Approach To Verifying The Closure Of Inspections, Tests, Analyses, And Acceptance Criteria (ITAAC) Through A Sample Based Inspection Program |
07-0047 |
06-0220 |
Final Rule to Update 10 CFR Part 52 |
|
06-0114 |
Description Of The Construction Inspection Program For Plants Licensed Under 10 CFR Part 52 |
|
06-0041 |
Proposed Strategy to Support Implementation of New Reactor Construction Inspection Program |
06-0041 |
05-0197 |
Review Of Operational Programs In A Combined License Application And Generic Emergency Planning Inspections, Tests, Analyses, and Acceptance Criteria |
05-0197 |
04-0032 |
Programmatic Information Needed For Approval Of A Combined License Without Inspections, Tests, Analyses, and Acceptance Criteria |
04-0032 |
02-0067 |
Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) For Operational Programs (Programmatic ITAAC) |
02-0067 |

Public Meetings
| Date |
Description |
| 12/18/07 |
Meeting to discuss the Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) closure letters and assessment and enforcement of postulated construction inspection findings
|
| 11/28/07 |
Meeting to discuss the Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) closure letters and assessment and enforcement of postulated construction inspection findings
|
| 10/18/07 |
Meeting to discuss the Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) closure letters and assessment and enforcement of postulated construction inspection findings
|
| 08/30/07, 08/31/07 |
Meeting to discuss the NRC monitoring of licensee performance, assessment of the results of NRC inspection activities, the Inspection Test Analysis and Acceptance Criteria (ITAAC) prioritization process and the ITAAC closure documentation requirements
|
| 01/25/07 |
Meeting with the Nuclear Energy Institute and Industry Stakeholders to Discuss Aspects of the Construction Inspection Program Related to the Nrc Monitoring and Assessment of Licensee Performance
|
| 01/23/07 |
Meeting with the Nuclear
Energy Institute to Discuss Inspection Manual Chapters (IMC)
2503 And 2504 of the Construction Inspection Program
|
| 05/04/05 |
Meeting with the
Nuclear Industry and the Public to Discuss
Categorization of Inspection Findings Related
to ITAAC
|
| 04/26/04 |
Meeting with NEI to Discuss CIP Information Management System (CIPIMS)
|
| 04/01/04 |
Meeting with NEI to Discuss CIPIMS Sample Schedules
|
| 02/13/04 |
Meeting with NEI to Discuss CIPIMS
|
| 01/29/04 |
Meeting with NEI to Discuss CIP and 10 CFR Part 52 Combined License Issues
|
| 01/15/04 |
Senior Management Meeting with NEI to Discuss CIP and 10 CFR Part 52 Combined License Issues
|
| 11/20/03 |
Meeting with NEI to Discuss CIP and 10 CFR Part 52 Combined License Issues
|
| 09/16/03 |
Meeting with Westinghouse to Discuss Construction Scheduling
|
| 08/27/03 |
Workshop to Discuss the Draft 10 CFR Part 52 CIP Framework Document
|
| 02/20/03 |
Meeting with NEI to Discuss the CIP and 10 CFR Part 52 COL
|
| 12/16/02 |
Meeting with Westinghouse to Discuss the Construction Schedule for New Reactors
|
| 08/22/02 |
Meeting with Bechtel to Discuss Construction Scheduling Software
|
| 08/20/02 |
Meeting with Westinghouse Electric Company to Discuss Construction Scheduling Software
|

Also see ITAAC discussion under New Reactors Licensing Process.

|