System Energy Resources Inc. application for an ESP for the Grand
Gulf site was submitted on
October 21, 2003. The contents of the application can be found below.
| Milestone |
Completion Date Actual - A Target - T |
| Receive early site permit application |
10/21/03 - A |
| Press Release announcing receipt and availability |
11/07/03 - A |
| Federal Register notice (FRN) published for receipt and availability |
11/14/03 - A |
| FRN published announcing acceptance |
12/01/03 - A |
| FRN published for Notice of Intent (environmental scoping process) |
12/31/03 - A |
| Press Release announcing acceptance |
01/13/04 - A |
| FRN published for mandatory hearing |
01/16/04 - A |
| Environmental scoping meeting |
01/21/04 - A |
| Scoping period ends |
02/12/04 - A |
| 1st inspection complete |
02/13/04 - A |
| Deadline for filing petitions for intervention |
02/17/04 - A |
| Environmental site audit |
04/16/04 - A |
| Deadline for submitting contentions |
05/03/04 - A |
| Environmental requests for additional information (RAIs) issued to applicant |
07/02/04 - A |
| Applicant submits response to environmental RAIs |
09/17/04 - A |
| Safety and emergency planning (EP) RAIs issued to the applicant |
09/21/04 - A |
| Applicant submits responses to safety and EP RAIs |
12/07/04 - A |
| Draft safety evaluation report (SER) issued |
04/07/05 - A |
| Draft environmental impact statement (EIS) to EPA, Issue Notice of Availability |
04/29/05 - A |
| ACRS subcommittee meeting on draft SER |
05/16/05 - A |
| ACRS full committee meeting on draft SER |
06/02/05 - A |
| Public meeting to discuss draft EIS |
06/14/05 - A |
| Applicant submits responses to SER open items |
06/21/05 - A |
| 2nd inspection complete |
06/23/05 - A |
| ACRS interim letter to Commission |
06/24/05 - A |
| End of draft EIS comment period |
07/14/05 - A |
| Optional final inspection complete |
N/A |
| Final SER issued |
10/21/05 - A |
| Regional Administrator's Letter |
N/A |
| ACRS full committee meeting on final SER |
12/08/05 - A |
| ACRS letter to Commission |
12/23/05 - A |
| Final EIS issued to EPA/Issue Notice of Availability |
04/07/06 - A |
| Final SER issued as NUREG |
04/14/06 - A |
| Atomic Safety and Licensing Board (ASLB) initial decision |
01/28/07 - A |
| Commission decision |
03/27/07 - A |