Public Meetings

Early Site Permits - System Energy Resources Inc. Application for the Grand Gulf ESP Site

System Energy Resources Inc. application for an ESP for the Grand Gulf site was submitted on October 21, 2003. The contents of the application can be found below.

On this page:

Application Information

Some links on this page are to documents in our Agencywide Documents Access and Management System (ADAMS), and others are to documents in Adobe Portable Document Format (PDF). ADAMS documents are provided in either PDF or Tagged Image File Format (TIFF). To obtain free viewers for displaying these formats, see our Plugins, Viewers, and Other Tools page. If you have questions about search techniques or problems with viewing or printing documents from ADAMS, please contact the Public Document Room staff.

(To top of page)

Review Schedule

Milestone Completion Date Actual - A
Target - T
Receive early site permit application 10/21/03 - A
Press Release announcing receipt and availability 11/07/03 - A
Federal Register notice (FRN) published for receipt and availability 11/14/03 - A
FRN published announcing acceptance 12/01/03 - A
FRN published for Notice of Intent (environmental scoping process) 12/31/03 - A
Press Release announcing acceptance 01/13/04 - A
FRN published for mandatory hearing 01/16/04 - A
Environmental scoping meeting 01/21/04 - A
Scoping period ends 02/12/04 - A
1st inspection complete 02/13/04 - A
Deadline for filing petitions for intervention 02/17/04 - A
Environmental site audit 04/16/04 - A
Deadline for submitting contentions 05/03/04 - A
Environmental requests for additional information (RAIs) issued to applicant 07/02/04 - A
Applicant submits response to environmental RAIs 09/17/04 - A
Safety and emergency planning (EP) RAIs issued to the applicant 09/21/04 - A
Applicant submits responses to safety and EP RAIs 12/07/04 - A
Draft safety evaluation report (SER) issued 04/07/05 - A
Draft environmental impact statement (EIS) to EPA, Issue Notice of Availability 04/29/05 - A
ACRS subcommittee meeting on draft SER 05/16/05 - A
ACRS full committee meeting on draft SER 06/02/05 - A
Public meeting to discuss draft EIS 06/14/05 - A
Applicant submits responses to SER open items 06/21/05 - A
2nd inspection complete 06/23/05 - A
ACRS interim letter to Commission 06/24/05 - A
End of draft EIS comment period 07/14/05 - A
Optional final inspection complete N/A
Final SER issued 10/21/05 - A
Regional Administrator's Letter N/A
ACRS full committee meeting on final SER 12/08/05 - A
ACRS letter to Commission 12/23/05 - A
Final EIS issued to EPA/Issue Notice of Availability 04/07/06 - A
Final SER issued as NUREG 04/14/06 - A
Atomic Safety and Licensing Board (ASLB) initial decision 01/28/07 - A
Commission decision 03/27/07 - A

(To top of page)

Safety Evaluation Report

NUREG-1840, "Safety Evaluation Report for an Early Site Permit (ESP) at the Grand Gulf Site"

(To top of page)

Environmental Impact Statement

NUREG-1817,"Environmental Impact Statement for an Early Site Permit (ESP) at the Grand Gulf ESP Site"

(To top of page)

Grand Gulf Early Site Permit

On April 5, 2007, the Grand Gulf Early Site Permit was issued for a site located approximately 25 miles south of the city of Vicksburg, Mississippi.

(To top of page)

Project Managers for Grand Gulf ESP Site Application

Project Managers Grand Gulf ESP Site Application
Site Safety George Wunder
Environmental James Wilson

(To top of page)