Design Certification Application Review - ESBWR

The Economic Simplified Boiling Water Reactor (ESBWR) is a 4500 MWt reactor that uses natural circulation for normal operation and has passive safety features. GE-Hitachi Nuclear Energy (GEH) submitted an application for final design approval and standard design certification for the ESBWR on August 24, 2005. By letter dated December 1, 2005, the application was accepted for docketing. Docket number 52-010 has been assigned to the ESBWR.

For additional information, please access our ADAMS Advanced Web Search. Enter 05200010 in the 'Docket Number' field to search for documents linked to the ESBWR design certification application."

Some links on this page are to documents in our Agencywide Documents Access and Management System (ADAMS), and others are to documents in Adobe Portable Document Format (PDF). ADAMS documents are provided in either PDF or Tagged Image File Format (TIFF). To obtain free viewers for displaying these formats, see our Plugins, Viewers, and Other Tools page. If you have questions about search techniques or problems with viewing or printing documents from ADAMS, please contact the Public Document Room staff.

On this page:

Design Certification Review

On September 28, 2007, GEH submitted Revision 4 to the ESBWR Design Control Document (DCD).

The ESBWR Probabilistic Risk Assessment (PRA) is also publicly available. See NEDO-33201, Revision 1, "ESBWR Probabilistic Risk Assessment."

(To top of page)

Application Review Schedule

The staff's review schedule for the ESBWR Design Certification was provided to GEH on November 27, 2007. On February 20, 2008, GEH updated their schedule for submittal of Revision 5 of the ESBWR Design Control Document. The staff is currently re-evaluating its review schedule based on this information.

Key Milestones Completion Date
Actual - A
Target - T
Application
Received design certification application 08/24/05 - A
 
Acceptance Review
Federal Register Notice (FRN) published for receipt and availability 09/28/05 - A
FRN published announcing acceptance 12/09/05 - A
Review schedule published  
 
Review
Advanced SER with no Open Items issued to ACRS  
Response to ACRS regarding SER with no Open Items issued  
Final SER issued  
 
Rulemaking
Issue proposed rule  
Issue final draft rule  
Issue final rule  

(To top of page)

Pre-Application Review

On April 18, 2002, GEH requested a pre-application review of the ESBWR. Since that time, the staff completed its review of the application of the TRACG thermal hydraulic code to ESBWR loss of coolant accidents . The staff is currently reviewing the application of the TRACG code for ESBWR anticipated operational occurrences (AOOs) and the application of TRACG to ESBWR thermal-hydraulic stability. These reviews will be completed as part of the design certification review.

For additional information, please access our ADAMS Advanced Web Search. Enter proj0717 in the 'Docket Number' field to search for documents linked to the ESBWR design certification application.

(To top of page)

Project Managers

NRC project managers assigned to the ESBWR design certification project.

ESBWR PMs
Lead Project Manager Amy Cubbage
Project Managers Bruce Bavol
Michael Eudy
Rocky Foster
Dennis Galvin
Andrea Johnson
Tom Kevern
Eric Oesterle
Chandu Patel
Leslie Perkins
Tom Tai
Mark Tonacci

(To top of page)



Privacy Policy | Site Disclaimer
Friday, April 18, 2008