North Anna, Unit 3 Application

Project Overview

North Anna
Who:   Dominion Virginia Power (Dominion)

What:   Application for a combined license (COL) for an Economic Simplified Boiling Water Reactor (ESBWR), the proposed North Anna Unit 3

When:   November 27, 2007 (date of application submittal)

Where:   Dominion's North Anna sites near Richmond in Louisa County, Virginia

On this page:

The following links on this page are to documents in our Agencywide Documents Access and Management System (ADAMS). ADAMS documents are provided in either Adobe Portable Document Format (PDF) or Tagged Image File Format (TIFF). To obtain free viewers for displaying these formats, see our Plugins, Viewers, and Other Tools. If you have problems with viewing or printing documents from ADAMS, please contact the Public Document Room staff.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

Dominion transmittal letter for North Anna Unit 3 COLA (November 27, 2007)

  • Part 1 – General and Administrative Information
  • Part 2 – Final Safety Analysis Report (FSAR)
  • Part 3 – Environmental Report
  • Part 4 – Technical Specifications
  • Part 5 – Emergency Plan
  • Part 6 – Part not used in this application
  • Part 7 – Departures (Variances, Supplemental Information) from the ESBWR Design Control Document (DCD)
  • Part 8 – Security Plan [This Part contains safeguards information which is withheld from public availability]
  • Part 9 – Part not used in this application
  • Part 10 – Tier 1/Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC)

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 11/27/07 - A
Acceptance Review
Acceptance Review Start
12/03/07 - A
Docketing Decision Letter Issued/Acceptance Review Complete
01/28/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
02/27/08 - A
Safety Review
Phase 1 –Requests for Additional Information (RAIs) Issued to Applicant
08/29/08 - T
Phase 2 – SER with Open Items issued
04/20/09 - T
Phase 3 – ACRS Review of SER with Open Items Complete
07/28/09 - T
Phase 4 – Advanced SER with no Open Items Issued
03/10 - T
Phase 5 – ACRS Review of SER with no Open Items Complete
07/10 - T
Phase 6 – Final SER Issued
08/10 - T
Environmental Review
Phase 1 – Environmental impact statement (EIS) summary report issued
08/05/08 - T
Phase 2 – Draft EIS issued to EPA
12/08 - T
Phase 3 – Response to public comments on draft EIS issued
06/09 - T
Phase 4 – Final EIS issued to EPA
12/09 - T
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register Notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found at NRC’s Website on Hearing Opportunities.

To top of page

NRC Documents

To top of page

Requests for Additional Information

Requests for Additional Information - Safety Applicant Response
RAI Letter 01 Response
RAI Letter 02 Response
RAI Letter 03 Response
RAI Letter 04  
RAI Letter 05  
RAI Letter 06  
RAI Letter 07  
RAI Letter 08  
RAI Letter 09  
RAI Letter 10  
RAI Letter 11  

Requests for Additional Information - Environmental Applicant Response
RAI Letter 01  

To top of page

Public Meetings

Date Description
04/16/08 Environmental Scoping
12/13 - 14/07 Meeting regarding the technical content of the North Anna 3 COLA
11/29/07 North Anna 3 COLA Orientation
10/24/07 Public Outreach Meeting

To top of page

Contacts

Contacts for North Anna COL Application
Safety Project Manager Thomas Kevern
Environmental Project Manager Alicia Williamson
Contact a Public Affairs Officer