Home > Nuclear
Reactors > New
Reactors > Plant Applications for Combined License > Calvert Cliffs, Unit 3 Application
Calvert Cliffs, Unit 3 Application
Project Overview
|
| Who: |
UniStar Nuclear and Constellation
|
| What: |
Application for a combined license (COL) for an AREVA U.S. Evolutionary Power Reactor (EPR), the proposed Calvert Cliffs Nuclear Power Plant Unit 3
|
| When: |
July 13, 2007 (date of initial application of Part 1 which included the Environmental Report)
|
| Where: |
Unistar's Calvert Cliffs site near Lusby in Calvert County, Maryland |
|
On this page:
The following links on this page are to documents in our Agencywide
Documents Access and Management System (ADAMS). ADAMS documents are provided
in either Adobe Portable Document Format (PDF) or Tagged Image File Format
(TIFF).
To obtain free viewers for displaying these formats, see our Plugins,
Viewers, and Other Tools. If you have problems
with viewing or printing documents from ADAMS, please contact the Public
Document
Room staff.
Reference Documents

Applicant Documents
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
UniStar transmittal letter for Calvert Cliffs Unit 3 COLA, Part II ( March 14, 2008)
- Part 1 – General and Administrative Information
- Part 2 – Final Safety Analysis Report (FSAR)
- Part 3 – Environmental Report
- Part 4 – Technical Specifications
- Part 5 – Emergency Plan
- Part 6 – Limited Work Authorization (LWA) [Part not used in this application]
- Part 7 – DCD Departures
- Part 8 – Security Plan [This Part contains safeguards information which is withheld from public availability]
- Part 9 – Proprietary and Sensitive Unclassified Non-Safeguards Information [This Part contains information which is withheld from public availability.]
- Part 10 – Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) and ITAAC Closure
- Part 11A – Quality Assurance Program Description
- Part 11B – AREVA Design Control Document
- Part 11C – DCD Supplements
- Part 11D – NEI Reference Documents [This Part contains information which is withheld from public availability.]
- Part 11E – Process Control Program
- Part 11F – Offsite Dose Calculation Manual
- Part 11G – Fuel Racks Report
- Part 11H – State and Local Emergency Plans [This Part contains information which is withheld from public availability.]
- March 14, 2008 supplement (Information Associated with Soil Hazard Curves at Additional Annual Exceedence Frequencies)
- March 3, 2008 supplement (Electronic Data Associated with the Probabilistic Seismic Hazards Analysis)
- January 14, 2008 revision to partial COL application
- December 14, 2007 revision to partial COL application
- October 30, 2007 response to acceptance review letter
- September 11, 2007 supplement (General Information Binder)
- August 2, 2007 supplement (ER Chapters 4 - 10)
- Calvert Cliffs COLA, Part I, July 13 and July 16, 2007 (FSAR Chapter 2, ER Chapters 1 - 3, Administrative Information)

Application Review Schedule
| Key Milestones |
Completion Date Actual - A Target - T |
| Acceptance Review |
Federal Register Notice (FRN) published for receipt and availability |
08/15/07 - A |
FRN published announcing acceptance |
01/31/08 - A |
FRN published for mandatory hearing |
TBD, Note 1 |
| Safety Review |
Phase 1 – Preliminary Safety Evaluation Report (SER) with Requests for Additional Information (RAIs) issued to applicant |
|
Phase 2 – SER with Open Items issued |
|
Phase 3 – Response to ACRS regarding SER with Open Items issued |
|
Phase 4 – Advanced SER with no Open Items issued |
|
Phase 5 – Response to ACRS regarding SER with no Open Items issued |
|
Phase 6 – Final SER issued as NUREG |
|
| Environmental Review |
Phase 1 – Environmental impact statement (EIS) summary report issued |
09/05/08 - T |
Phase 2 – Draft EIS issued to EPA |
02/09/09 - T |
Phase 3 – Response to public comments on draft EIS issued |
11/10/09 - T |
Phase 4 – Final EIS issued to EPA |
03/01/10 - T |
| Hearing |
Commission or ASLB hold mandatory hearing |
|
| License |
Commission decision on issuance of COL application |
|
Note 1: TBD pending completion of acceptance review of Part 2 of the application which was submitted on March 17, 2008.

NRC Documents

Public Meetings
| Date |
Description |
| 03/19/08 |
Public Environmental Scoping Meeting
|
| 08/14/07 |
Public Outreach
|

Contacts

|