Application Review Schedule for Smith Ranch Highland
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Power Resources, Inc. submitted to renew its license for the Smith Ranch Highland In Situ Recovery (ISR) site.
| Key Milestones | Completion Date Actual - A Target - T |
|---|---|
| Application Tendered | 02/1/2012 – A |
| Acceptance Review | |
Acceptance Review Start |
02/9/2012 – A |
Docketing Decision Letter Issued/Acceptance Review Complete |
07/5/2012 – A |
| Safety Review * | |
Requests for Additional Information (RAIs) Issued to Applicant |
05/02/2013 – A |
Safety Evaluation Report (SER) completed |
TBD |
| Environmental Review * | |
RAIs Issued |
05/02/2013 – A |
Final EA issued |
TBD |
| License | |
Licensing Action Completed - License Issued |
TBD |
* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.