Application Review Schedule for Reno Creek

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that AUC, LLC submitted to obtain a license for its Reno Creek In Situ Recovery site.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 10/05/12
Acceptance Review
Acceptance Review Start
03/18/13 - A
Docketing Decision Issued/Acceptance Review Complete
06/18/13 - A
Safety Review *
Requests for Additional Information (RAIs) Issued to Applicant
01/20/14 - T
Final Draft Safety Evaluation Report (SER) completed
TBD
Environmental Review *
RAIs Issued
TBD
Draft SEIS issued
TBD
Public comment period ends
TBD
Final SEIS issued
TBD
License
Licensing Action Completed - License and Final SER Issued
TBD

* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.