Application Review Schedule for Marsland

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Cameco (Crow Butte Resources) submitted to obtain a license for its Marsland In Situ Recovery site.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 06/20/12 -A
Acceptance Review
Acceptance Review Start
08/06/12 - A
Docketing Decision Issued/Acceptance Review Complete
10/05/12 - A
Safety Review *
Requests for Additional Information (RAIs) Issued to Applicant
06/28/13 - T
Safety Evaluation Report (SER) completed
02/04/15 - T
Environmental Review *
Requests for Additional Information (RAIs) Issued to Applicant
05/07/13 - T
Draft EA issued to Nebraska DEQ
01/31/14 - T
Final EA issued to Nebraska DEQ
03/31/14 - T
License
Licensing Action Completed - License Issued
02/04/15 - T

* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.