Application Review Schedule for Marsland
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Cameco (Crow Butte Resources) submitted to obtain a license for its Marsland In Situ Recovery site.
| Key Milestones | Completion Date Actual - A Target - T |
|---|---|
| Application Tendered | 06/20/12 -A |
| Acceptance Review | |
Acceptance Review Start |
08/06/12 - A |
Docketing Decision Issued/Acceptance Review Complete |
10/05/12 - A |
| Safety Review * | |
Requests for Additional Information (RAIs) Issued to Applicant |
06/28/13 - T |
Safety Evaluation Report (SER) completed |
02/04/15 - T |
| Environmental Review * | |
Requests for Additional Information (RAIs) Issued to Applicant |
05/07/13 - T |
Draft EA issued to Nebraska DEQ |
01/31/14 - T |
Final EA issued to Nebraska DEQ |
03/31/14 - T |
| License | |
Licensing Action Completed - License Issued |
02/04/15 - T |
* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.