Application Review Schedule for Ludeman
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Uranium One submitted to obtain a license for its Ludeman In Situ Recovery site.
| Key Milestones | Completion Date Actual - A Target - T |
|---|---|
| Application Received | 12/6/11 |
| License Application in ADAMS | 1/3/12 - A |
| Acknowledgement Letter Sent | 12/20/11 - A |
| SUNSI Review Completed (5 work days from entry into ADAMS) | 1/10/12 - A |
| Acknowledgement email Sent (11 days from receipt) | 12/19/11 – A |
| Acceptance Review Begins (Established by Management Priority) | 1/3/12 - A |
| Acceptance Review Complete (60 days from Acceptance Review Begins) | 5/16/12 - A |
| RAIs / Draft SER Complete | 1/19/13 - A |
| Complete SER (180 days from RAI Response) | 11/28/13 - T |
| Environmental Review | |
Requests for RAIs to Applicant |
1/19/13 - A |
Final Environmental Document Issued |
TBD |
| Issue License Amendment | 1/14/14 - T |
* Actual Time Depends on Licensee