Application Review Schedule for Dewey Burdock

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Powertech Uranium Company submitted to obtain a license for its Dewey Burdock In Situ Recovery site.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 2/25/09 – A
Application Withdrawn 6/11/09 – A
Application Resubmitted 8/10/09 – A
Acceptance Review
Acceptance Review Start
8/10/09 – A
Docketing Decision Letter Issued/Acceptance Review Complete
10/2/09 – A
Safety Review *
Requests for Additional Information (RAIs) Issued to Applicant
5/28/10 – A
Final Safety Evaluation Report (SER) completed
03/2013 –A
Environmental Review
RAIs Issued to Applicant
4/14/10 – A
Draft SEIS issued
11/2012 – A
Public comment period
1/2013 – A
Final SEIS issued to EPA
10/2013 – T
License
Licensing Action Completed
11/2013 – T

* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.