AREVA Enrichment Services, LLC Gas Centrifuge Facility Licensing Review Schedule

Based on the Commission’s order, dated July 23, 2009, the NRC staff has developed the following schedule to complete the license application review for the AREVA Enrichment Services Eagle Rock Enrichment Facility within 30 months. This schedule is also available as a dataset with an accompanying data dictionary (both in Microsoft Excel format).

(Last updated – 02/25/2011)

DATE STATUS ACTION NOTE
12/30/2008 Completed Submits enrichment facility License Application and Environmental Report.  
3/12/2009 Completed NRC completes acceptance review of application.  
4/23/2009 Completed Submits revised application.  
4/30/2009 Completed NRC completes acceptance review of revised application.  
5/4/2009 Completed NRC issues notice of intent to prepare an Environmental Impact Statement (EIS) and notice of scoping meetings.  
6/4/2009 Completed NRC conducts EIS scoping meetings.  
6/18/2009 Completed Submits exemption request for early construction.  
7/7/2009 Completed Submits supplement to Environmental Report.  
7/23/2009 Completed Submits supplement to Environmental Report (groundwater sampling).  
8/18/2009 Completed Submits supplement to Environmental Report (depth to groundwater).  
7/30/2009 Completed NRC issues Schedule and Notice of Opportunity for Public Hearing.  
8/27/2009 Completed NRC completes technical review of Environmental Report/issues Request for Additional Information (RAI).  
9/9/2009 Completed NRC issues RAI for License Application.  
8/27/2009 Completed Responds to Environmental Report RAI.  
9/11/2009 Completed NRC issues EIS scoping summary report.  
9/14/2009 Completed NRC issues RAI for exemption request for early construction.  
9/28/2009 Completed Responds to License Application RAI.  
10/15/2009 Completed Responds to RAI for exemption request.  
10/15/2009 Completed Submits supplement to Environmental Report on preconstruction impacts.  
3/17/2010 Completed NRC issues final action on exemption request for early construction.  
7/23/2010 Completed NRC issues draft EIS for public comment.  
09/13/2010 Completed Draft EIS public comment period ends.  
09/28/2010 Completed NRC issues Safety Evaluation Report (SER).  
02/25/2011 Completed NRC issues final EIS and publishes notice of availability.  
No Later than 1/2012 Pending Commission issues final decisions. Date depends on the schedule set by the Licensing Board and consistent with the Hearing Order that final Commission decision is no later than January 2012.