AREVA Enrichment Services, LLC Gas Centrifuge Facility Licensing Review Schedule
Based on the Commission’s order, dated July 23, 2009, the NRC staff has developed the following schedule to complete the license application review for the AREVA Enrichment Services Eagle Rock Enrichment Facility within 30 months. This schedule is also available as a dataset with an accompanying data dictionary (both in Microsoft Excel format).
(Last updated – 02/25/2011)
| DATE | STATUS | ACTION | NOTE |
|---|---|---|---|
| 12/30/2008 | Completed | Submits enrichment facility License Application and Environmental Report. | |
| 3/12/2009 | Completed | NRC completes acceptance review of application. | |
| 4/23/2009 | Completed | Submits revised application. | |
| 4/30/2009 | Completed | NRC completes acceptance review of revised application. | |
| 5/4/2009 | Completed | NRC issues notice of intent to prepare an Environmental Impact Statement (EIS) and notice of scoping meetings. | |
| 6/4/2009 | Completed | NRC conducts EIS scoping meetings. | |
| 6/18/2009 | Completed | Submits exemption request for early construction. | |
| 7/7/2009 | Completed | Submits supplement to Environmental Report. | |
| 7/23/2009 | Completed | Submits supplement to Environmental Report (groundwater sampling). | |
| 8/18/2009 | Completed | Submits supplement to Environmental Report (depth to groundwater). | |
| 7/30/2009 | Completed | NRC issues Schedule and Notice of Opportunity for Public Hearing. | |
| 8/27/2009 | Completed | NRC completes technical review of Environmental Report/issues Request for Additional Information (RAI). | |
| 9/9/2009 | Completed | NRC issues RAI for License Application. | |
| 8/27/2009 | Completed | Responds to Environmental Report RAI. | |
| 9/11/2009 | Completed | NRC issues EIS scoping summary report. | |
| 9/14/2009 | Completed | NRC issues RAI for exemption request for early construction. | |
| 9/28/2009 | Completed | Responds to License Application RAI. | |
| 10/15/2009 | Completed | Responds to RAI for exemption request. | |
| 10/15/2009 | Completed | Submits supplement to Environmental Report on preconstruction impacts. | |
| 3/17/2010 | Completed | NRC issues final action on exemption request for early construction. | |
| 7/23/2010 | Completed | NRC issues draft EIS for public comment. | |
| 09/13/2010 | Completed | Draft EIS public comment period ends. | |
| 09/28/2010 | Completed | NRC issues Safety Evaluation Report (SER). | |
| 02/25/2011 | Completed | NRC issues final EIS and publishes notice of availability. | |
| No Later than 1/2012 | Pending | Commission issues final decisions. | Date depends on the schedule set by the Licensing Board and consistent with the Hearing Order that final Commission decision is no later than January 2012. |
Page Last Reviewed/Updated Thursday, March 29, 2012