4Q/2011 Performance Summary

Fort Calhoun has been shutdown since April 2011. Because the Unplanned Scrams with Complications (USwC) and Mitigating Systems Performance Index (MSPI) performance indicators (PIs) are heavily influenced by the operational status of the reactor, NRC staff has evaluated the validity of these PIs. Because the reactor has not been critical, there have been no recent opportunities for a scram that would count in the USwC indicator. Similarly, the MSPI values can become skewed because of a lack of critical hours. For these reasons, the staff has determined that these PIs no longer provide valid indications of performance.